MahaRERA Property Intelligence · Palghar

MANNAT REGENCY

P99000077898 · JAWHAR · promoter Himanshu Sham Tendulkar

Certificate SignedDue 30 Apr 2029

Delivery & Registration

MahaRERA registrationP99000077898
Registered on13 Nov 2024
Promoter-declared completion30 Apr 2029
Current statusCertificate Signed
Against today33 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Himanshu Sham Tendulkar is the promoter of record on 12 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
MANNAT REGENCY1G+7-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at JAWHAR, NEHARU CHAWK, Jawhar, Palghar, 401603. Per the filed land record, the plot is bounded to the north by C T S NO 375 373, to the south by 12 MTR D P ROAD, to the east by C T S NO 428 and to the west by D P ROAD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~95 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park95 km
Andheri MIDC / SEEPZ95 km
Chhatrapati Shivaji Int'l Airport99 km
Bandra Kurla Complex (BKC)101 km
Lower Parel / Worli business district110 km
Nariman Point / Fort118 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Himanshu Sham Tendulkar is the promoter on 9 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

See every Himanshu Sham Tendulkar project & its RERA track record →

Other flagged projects by Himanshu Sham Tendulkar

Himanshu Sham Tendulkar
FlaggedPalghar
Himanshu Sham Tendulkar
FlaggedPalghar
Himanshu Sham Tendulkar
FlaggedPalghar
Himanshu Sham Tendulkar
FlaggedPalghar
Himanshu Sham Tendulkar
FlaggedPalghar
Himanshu Sham Tendulkar
FlaggedPalghar

Other RERA-registered projects in Jawhar

Durvankur Heights
possession by May 2028 · Himanshu Sham Tendulkar
THE Empire
declared completion Mar 2026 · Shahji Infra
Gulmohar Avenue
declared completion Apr 2025 · Himanshu Sham Tendulkar
Spandan Landmark Residency
declared completion Dec 2024 · Imran Haji Yusuf Jummani
Noor Residency
Past its declared completion date · declared completion Dec 2024 · New Creative Construction
Shree Ganesh Heritage
declared completion Oct 2024 · Himanshu Sham Tendulkar

Other RERA-registered projects in Palghar

Manoshi Majethia Park Chsl
declared completion Aug 2023 · MAA Guru Developers
Mansarovar
declared completion Dec 2023 · Rudra Infra
Mansi Apartmrnt
declared completion Feb 2021 · Anmol Developers
Maple Terraces Building No. A-15
declared completion Dec 2021 · Messrs. Axis Dwellings LLP
Maple Terraces Building No. B-10
declared completion Dec 2021 · Messrs. Axis Dwellings LLP
Maple Terraces Building No. B-11
declared completion Dec 2021 · Messrs. Axis Dwellings LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026