MahaRERA Property Intelligence · Raigarh

MAULI KRIPA

P52000030719 · MIRCHI GULLY, ALIBAG · promoter Nitin Suryakant Mhatre

Certificate SignedDue 31 Aug 2025

Delivery & Registration

MahaRERA registrationP52000030719
Registered on08 Sep 2021
Promoter-declared completion31 Aug 2025
Current statusCertificate Signed
Against todayabout 11 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Nitin Suryakant Mhatre is the promoter of record on 32 projects, of which 5 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
MAULI KRIPA1G+531 Aug 2025

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at MIRCHI GULLY, ALIBAG, MIRCHI GULLY, NEAR VITHOBA MANDIR ALIBAG, Alibag, Raigarh, 402201. Per the filed land record, the plot is bounded to the north by 9 M WIDE DP ROAD, to the south by LANE, to the east by CTS 397 396 398 and to the west by LANE. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Nitin Suryakant Mhatre is the promoter on 5 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Nitin Suryakant Mhatre

Nitin Suryakant Mhatre
FlaggedRaigarh
Nitin Suryakant Mhatre
FlaggedRaigarh
Nitin Suryakant Mhatre
FlaggedRaigarh
Nitin Suryakant Mhatre
Not filing quarterly progress reportsRaigarh

Other RERA-registered projects in Alibag

Prajyot Devasthal
possession by Sep 2026 · Gaurav Pravin Gharat
Excellensea Villas Project
possession by Dec 2026 · Unicorp Realty Private Limited
Balibaug Rekreasi
possession by Dec 2026 · Pushpam Infra LLP
Ekaante Phase 3
possession by Dec 2026 · Green Park Developers
Lakshminarayan CO-OP Housing Society LTD Proposed
possession by Dec 2026 · Elnube Realtors PVT LTD
Sukh Shanti Residential Project
possession by Dec 2026 · SRS Developers

Major developers building in Alibag

Other RERA-registered projects in Raigarh

Mauli Krupa
declared completion Feb 2020 · Laxman Keshav Naik
Mauli Krupa
declared completion Jun 2023 · AAI Mauli Developers
Mauli Laxmi Puja
possession by Mar 2029 · Not Available
Mauli Nalanda
declared completion Jan 2020 · Sachin Kashinath Shigvan
Mauli Niwas
possession by Mar 2028 · Pandurang Sukir Koli
Mauli Plaza
possession by May 2027 · Mauli Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026