Mumbai/Project record

MahaRERA · the public record

MAULI MADHUSUDHAN

NEAR SIDDESHWAR HOSPITAL · RAMESHWAR YASHWANT PATIL

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700020637

Delivery and registration

When is the project declared for completion?

MAULI MADHUSUDHAN is registered with MahaRERA as P51700020637 and the promoter has declared completion for 31 Dec 2025.

31 Dec 2025

declared completion

9months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700020637
Registered on30 Apr 2019
Promoter-declared completion31 Dec 2025
Current statusCertificate Signed
Against todayabout 9 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for MAULI MADHUSUDHAN record 27 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Rameshwar Yashwant Patil is the promoter of record on 18 projects registered with MahaRERA, 5 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

18projects

registered with MahaRERA

5flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for MAULI MADHUSUDHAN in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
MAULI MADHUSUDHAN1G+731 Mar 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2025We have Registered our project with Maharera in 2019 declaring Proposed Date of Completion as 30/03/2023. As you are aware of the fact that by the end of the financial year 2019-20

Location, Land & Connectivity

Located at NEAR SIDDESHWAR HOSPITAL, VASUNDARI ROAD, Kalyan, Thane, 421605. Per the filed land record, the plot is bounded to the north by S NO 23 H NO 7, to the south by S NO 25, to the east by S NO 23 H NO 5 and to the west by BUILDING 1 OF 2 PHASE. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~14 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Powai / Hiranandani business park14 km
Andheri MIDC / SEEPZ15 km
Chhatrapati Shivaji Int'l Airport19 km
Bandra Kurla Complex (BKC)20 km
Lower Parel / Worli business district29 km
Nariman Point / Fort36 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Titwala

Ganpati Heights
possession by Sep 2026 · Manoj Prabhakar Patil
Indrayani
possession by Oct 2026 · Naresh Yashwant Patil
Mantra
possession by Nov 2026 · Vaidikh Nirmaan LLP
Rusttagi Aarambha 2.0
possession by Nov 2026 · Rustagi Estates Private Limited
Ganpati Prasanna
possession by Dec 2026 · Vijay Prabhakar Patil
Hillcrest Appartments
possession by Dec 2026 · Aasanghar Construction

Other RERA-registered projects in Thane

Mauli Nidhi
possession by Dec 2026 · Mauli Enterprises
Mauli Park
possession by Mar 2028 · M/s. Mauli Developers
Mauli Pride
possession by Dec 2027 · Mauli Krupa Developers
Mauli Sadan
possession by Dec 2026 · Mauli Construction
Mavis Tower A Wing From 5th Floor To 7th Floor
declared completion Dec 2019 · M/s. Unit Arsen Developers
Maximus
declared completion Dec 2025 · Guruvidha Enterprises

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026