MahaRERA Property Intelligence · Raigarh

MEGA CITY HOMES

P52000028334 · Lowjee · promoter Megacity Homes

Certificate SignedDue 30 Sep 2024

Delivery & Registration

MahaRERA registrationP52000028334
Registered on18 Feb 2021
Promoter-declared completion30 Sep 2024
Current statusCertificate Signed
Against todayabout 22 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Sales & Inventory

Of 108 homes filed with MahaRERA, 0 are sold/booked and 108 remain available (~0% sold) — early in sales — more choice of units now, but confirm the developer has the pre-sales to fund the build. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7 and 108 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Building No -1 - A B C Wings1G+79431 Mar 2024
Building No -2 D Wing1G+51431 Mar 2024

Unit mix on the filing: 108 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Lowjee, City Survey No - 1685 , Thane, Thane, 410203. Per the filed land record, the plot is bounded to the north by CTS No -1774, to the south by 9 mtr Wide Road, to the east by CTS No -1683 and to the west by Adjoining Nala. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Khopoli

Daata Eklavya Building A & B
possession by Aug 2026 · Daata Builders And Developers Private Li
Krishna Valley - Phase 3
possession by Aug 2026 · Prishti Venture Private Limited
Sanskruti
possession by Sep 2026 · Sandip Shankar Patil
Amansara Earthstar
possession by Nov 2026 · SVB Lifespaces LLP
Amansara Earthstar PH
possession by Nov 2026 · SVB Lifespaces LLP
Riddhi Siddhi Complex
Not filing quarterly progress reports · possession by Dec 2026 · Riddhi Siddhi Developers

Major developers building in Khopoli

Other RERA-registered projects in Raigarh

Mega Ista
declared completion Mar 2018 · Mohammed Yusuf Salim Chaudhary
Mega Nexus
declared completion Mar 2019 · Mohammed Yusuf Salim Chaudhary
Mega Vista
possession by Dec 2026 · Mohammed Yusuf Salim Chaudhary
Megha Corner
possession by Dec 2026 · Megha Builders & Developers
Meghna Bliss
possession by Dec 2026 · Meghna Builders
Meghna City
possession by Dec 2026 · Meghna Builders

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026