MahaRERA Property Intelligence · Mumbai Suburban

MINNAT APARTMENT

P51800013658 · promoter Hindustan Builder

Certificate SignedDue 30 Dec 2023

Delivery & Registration

MahaRERA registrationP51800013658
Registered on16 Oct 2017
Promoter-declared completion30 Dec 2023
Current statusCertificate Signed
Against todayabout 31 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Hindustan Builder is the promoter of record on 9 projects, of which 2 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
MINNAT APRTMENT1G+8-

Complaints & Orders

5 complaints are on the MahaRERA record for this project, with orders passed in 5. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000002285805/02/2018TUFAILAHMEDKHAN vs Hindustan builderorder passed
CC00600000011091014/09/2019Abdul Asad Abdul Samad Siddiqui vs Hindustan Buildersorder passed
CC00600000019683226/04/2021Mrs. Mable Hubert Pereira vs Hindustan Buildersorder passed
CC00600000019683826/04/2021Mrs. Elezabeth@Elizabeth Peter Farro vs Hindustan Buildersorder passed
CC00600000030337223/11/2022SOEB MANTRI MANTRI vs HINDUSTAN BUILDERorder passed

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Bombay High Court1522011Consent Term

Location, Land & Connectivity

Located at Kurla, Mumbai Suburban, 400070. Per the filed land record, the plot is bounded to the north by PATHWAY, to the south by 864, to the east by DP ROAD and to the west by 859 PART. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~1 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Bandra Kurla Complex (BKC)1 km
Chhatrapati Shivaji Int'l Airport2 km
Powai / Hiranandani business park6 km
Andheri MIDC / SEEPZ6 km
Lower Parel / Worli business district10 km
Nariman Point / Fort18 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kurla West

Sayba Arcadia
possession by Jul 2026 · Star Empire
JAI Shreeram Prasanna Chsl
possession by Aug 2026 · Riyaz Ramzan Shah
Sanjary Apartments
possession by Aug 2026 · R Shah Enterprises Private Limited
Yojan One
possession by Sep 2026 · Meru Realty LLP
Imperial Heights
possession by Nov 2026 · Sumukha Realtors
BKC Crown
possession by Dec 2026 · Shreeji Properties

Major developers building in Kurla West

Other RERA-registered projects in Mumbai Suburban

Mint
declared completion Jun 2026 · Tulsiani Sumer Associates
MIO Miraya
possession by Dec 2028 · Sayaji Realty Private Limited
MIO Solace
possession by Dec 2028 · Hariom Sayaji Properties LLP
Mirabilis
declared completion Dec 2023 · Skylink Hospitality LLP
Mirai
possession by Mar 2027 · Graceunited Developers
Miraya Residency
declared completion Jun 2026 · S M A Q Infra LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026