MahaRERA Property Intelligence · Thane

Mohan Samah

P51700053276 · Sarsole,Nerul · promoter Constructions

Certificate SignedDue 31 Dec 2027

Delivery & Registration

MahaRERA registrationP51700053276
Registered on23 Oct 2023
Promoter-declared completion31 Dec 2027
Current statusCertificate Signed
Against today17 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+9.

BuildingWingsFloorsDeclared completion
Mohan Samah1G+9-

Complaints & Orders

1 complaint is on the MahaRERA record for this project, with orders passed in 0. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC1260265808/05/2026Alpa Mahesh Sharma vs V M Constructionspending / no order on file

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. 1 is still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Belapur Court156/20232024Pending

Location, Land & Connectivity

Located at Sarsole,Nerul , Sector No- 6, Thane, Thane, 400706. Per the filed land record, the plot is bounded to the north by 35 meter wide road, to the south by 6 meter wide road, to the east by Plot no- 11 and to the west by Plot No-13. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Nerul

Vishv Eleanor
possession by Aug 2026 · Vishv Realty
Cyber Code
possession by Sep 2026 · Greenscape Realty
Shreeji Dios
possession by Dec 2026 · Shreeji Ventures Nirmaan Private Limited
Infinity Ikon
possession by Dec 2026 · Emperia Projects
Plan I
possession by Dec 2026 · M/s. Tescon Plan-I LLP
Regency Palms Phase IV
possession by Dec 2026 · Regency INC

Other RERA-registered projects in Thane

Mohan Skyville
declared completion Jun 2023 · Mohan Lifespaces LLP
Mohan Suburbia IIB
declared completion Mar 2019 · Mohan Lifespaces LLP
Mohan Suburbia III
declared completion Aug 2023 · Mohan Lifespaces LLP
Mohan Suburbia IV
declared completion Dec 2020 · Mohan Lifespaces LLP
Mohan Suburbia IV NX
possession by Dec 2027 · Mohan Lifespaces LLP
Mohan Tribeca
possession by Dec 2026 · Mohan Lifespaces LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026