Mumbai/Project record

MahaRERA · the public record

Muktanand Co-op Housing Society

Kurla West · Kuldeep s Pednekar

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

01 May 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

01 May 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800006384

Delivery and registration

When is the project declared for completion?

Muktanand Co-op Housing Society is registered with MahaRERA as P51800006384 and the promoter has declared completion for 01 May 2022.

01 May 2022

declared completion

52months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800006384
Registered on14 Aug 2017
Promoter-declared completion01 May 2022
Current statusCertificate Signed
Against todayabout 52 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Muktanand Co-op Housing Society record 20 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 20 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Kuldeep Pednekar is the promoter of record on 3 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

3projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Muktanand Co-op Housing Society in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
Muktanand Co-opHousing Society1G+5-

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for Muktanand Co-op Housing Society, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000004442406/05/2018Ganesh Narayan Gujeti vs Ismail Amduleorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.

FromExtended toStated reason
as registered30 Apr 2020Delay in receiving the aviation permission for the desired height to consume permissible FSI.
30 Apr 202030 Apr 2020Transferring Property card in the name of MCGM and GVK Misinterpretation.
30 Apr 202001 Nov 2021Cannot get in touch with the GVK Officials due to this pandemic.

Location, Land & Connectivity

Located at Kurla West, Ward FSouth, Mumbai City, 400070. Per the filed land record, the plot is bounded to the north by 827, to the south by 830, to the east by 829 and to the west by Road. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~1 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Bandra Kurla Complex (BKC)1 km
Chhatrapati Shivaji Int'l Airport2 km
Powai / Hiranandani business park6 km
Andheri MIDC / SEEPZ6 km
Lower Parel / Worli business district10 km
Nariman Point / Fort18 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kurla West

Yojan One
possession by Sep 2026 · Meru Realty LLP
Imperial Heights
possession by Nov 2026 · Sumukha Realtors
Buddha Vihar CHS LTD
possession by Dec 2026 · M/S Regal Builders AND Developers
Khaliliya Complex
possession by Dec 2026 · Dani Builders AND Developers
Mantri Business Plaza
possession by Dec 2026 · Mantri Brothers
Rehmaniya Apartments
possession by Dec 2026 · S & S Enterprises

Major developers building in Kurla West

Other RERA-registered projects in Mumbai Suburban

Muktangan Residency
possession by Oct 2027 · Raaz Mohammed Abdul Samad Pathan
Mulund CHS LTD
declared completion Feb 2024 · Yashraj Corporation
Mulund Giriraj Chsl
declared completion Dec 2025 · Anon Developers
Mulund Laxmi Narayan Chsl
possession by Mar 2027 · Bhushan Anant Vichare
Mulund Mahavirdham CO. OP. Housing Soc. LTD
declared completion Oct 2023 · Maverick Realtors
Mulund Neeta
possession by Jun 2030 · Titan Maverick Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026