MahaRERA Property Intelligence · Palghar

MYZO SUITES BUILDING NO 3 - A WING

P99000046656 · BHOPOLI · promoter Ayush Reality

Certificate SignedDue 31 Dec 2027

Delivery & Registration

MahaRERA registrationP99000046656
Registered on26 Aug 2022
Promoter-declared completion31 Dec 2027
Current statusCertificate Signed
Against today17 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
MYZO SUITES BUILDING NO 3 - A WING TYPE B1G+531 Dec 2027

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at BHOPOLI, BHOPOLI, Vasai, Palghar, 401403. Per the filed land record, the plot is bounded to the north by G NO 81, to the south by G NO 50 57, to the east by ROAD and to the west by G NO 48. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Manor

15 Manor - Belvedere 2
possession by Dec 2026 · RV Infra
Myzo Suites
possession by Dec 2027 · Myzo Infra Private Limited
Godrej Country Estate
declared completion Apr 2026 · Godrej Projects Development Limited
Bandhan Heritage Phase II
Not filing quarterly progress reports · declared completion Dec 2025 · Mahi Links
Riddhi Siddhi Park Phase-2
Past its declared completion date · declared completion Jun 2024 · Riddhi Siddhi Builders
Mahim Garden
declared completion Dec 2023 · Karan Builders & Developers

Other RERA-registered projects in Palghar

N G Platinum City
possession by Dec 2026 · J M G Realtors PVT LTD
N G Platinum City Phase IV
possession by Dec 2027 · J M G Realtors PVT LTD
N G Platinum City Phase V
possession by Mar 2030 · J M G Realtors PVT LTD
N G Shree RAM VAN Phase I
declared completion Dec 2020 · J M G Realtors PVT LTD
N G Shree RAM VAN Phase II
declared completion Sep 2021 · J M G Realtors PVT LTD
N K Heights
declared completion Jan 2025 · Maxtech Infra Tech Pvt.ltd.

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026