Mumbai/Project record

MahaRERA · the public record

NEELKANTH RESIDENCY

Thane · DEEPJYOTI INFRA DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

25 Dec 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

25 Dec 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000005307

Delivery and registration

When is the project declared for completion?

NEELKANTH RESIDENCY is registered with MahaRERA as P52000005307 and the promoter has declared completion for 25 Dec 2024.

25 Dec 2024

declared completion

21months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000005307
Registered on11 Aug 2017
Promoter-declared completion25 Dec 2024
Current statusCertificate Signed
Against todayabout 21 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for NEELKANTH RESIDENCY record 30 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 30 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Deepjyoti Infra Developers is the promoter of record on 3 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

3projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for NEELKANTH RESIDENCY in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
A Building1G+430 Dec 2022
B Building1G+430 Dec 2022
C Building1G+430 Dec 2022
D Building1G+430 Dec 2022
E Building1G+430 Dec 2022
F Building1G+430 Dec 2022

Legal and disputes

What disputes are disclosed?

2 complaints are on the MahaRERA record for NEELKANTH RESIDENCY, with orders passed in 2 of them.

2complaints

2with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000019376919/08/2020Baburao Chougule vs RAJENDRA S UTEKARorder passed
CC00600000019828611/10/2021Ajit Vishwanath Taralkar vs M/s Deepjyoti Infra Developersorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 4 times, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2021There are total 232 Units in our Neelkanth Residency Project and so far (as on 31/12/2019) 161 Units have been booked. We have obtained consent of 101 customers for extending t
31 Dec 202131 Dec 2021i) 70% work of the project is already completed and striving for completion of remaining work as fast as possible. ii) Though demonetization took place in the year 2016 and GST w
31 Dec 202130 Jun 2023To, The Secretary, Maharashtra Real Estate Regulatory Authority 6th & 7th Floor, Housefin Bhavan, Plot No: C - 21, E - Block, Bandra Kurla Complex, Bandra (E), Mumbai 400
30 Jun 202325 Dec 2024Due to medical reason

Location, Land & Connectivity

Located at Thane, Thane, 410201. Per the filed land record, the plot is bounded to the north by Survey No 32, to the south by Survey No 33 Part 6 A, to the east by Survey No 33 Part 9 and to the west by Survey No 33 Part 6 B. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~50 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park50 km
Bandra Kurla Complex (BKC)51 km
Chhatrapati Shivaji Int'l Airport52 km
Nariman Point / Fort53 km
Lower Parel / Worli business district53 km
Andheri MIDC / SEEPZ54 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Deepjyoti Infra Developers is the promoter on 2 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Deepjyoti Infra Developers

Deepjyoti Infra Developers
Past its declared completion dateRaigarh

Other RERA-registered projects in Karjat

Dhanlaxmi Heights
possession by Sep 2026 · Dhanlaxmi Developers
Warai Woods Ph 2
Not filing quarterly progress reports · possession by Nov 2026 · Nahar Riddhi Siddhi Developers
Jambrung Valley
possession by Nov 2026 · Kirtiraj Nanasaheb Sawant
Bliss Studio
possession by Dec 2026 · Balsam Builders
Beverly Hills
possession by Dec 2026 · Rudram Infra Projects Private Limited
Jupiter Heights
Not filing quarterly progress reports · possession by Dec 2026 · Jupiter Heights

Major developers building in Karjat

Other RERA-registered projects in Raigarh

Neelkanth Residency
declared completion Jan 2019 · Neelkanth Enterprises
Neelkanth Rudra
possession by Dec 2028 · Khushboo Enterprises
Neelkanth Sanskruti
declared completion Dec 2019 · Neelkanth Constructions
Neelkanth Shiv
possession by Dec 2030 · Neelkanth Developers
Neelkanth Solitaire
possession by Dec 2030 · Sankalp Realtors
Neelkanth Stella
possession by Dec 2028 · Neelkanth Infracon

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026