Mumbai/Project record

MahaRERA · the public record

NEELKANTHDHARA

GHATKOPAR WEST · ASHAPURA DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800007105

Delivery and registration

When is the project declared for completion?

NEELKANTHDHARA is registered with MahaRERA as P51800007105 and the promoter has declared completion for 30 Dec 2025.

30 Dec 2025

declared completion

9months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800007105
Registered on17 Aug 2017
Promoter-declared completion30 Dec 2025
Current statusCertificate Signed
Against todayabout 9 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for NEELKANTHDHARA record 34 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Ashapura Developers is the promoter of record on 58 projects registered with MahaRERA, 5 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

58projects

registered with MahaRERA

5flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for NEELKANTHDHARA in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+9.

BuildingWingsFloorsDeclared completion
NEELKANTHDHARA A B AND C WING1G+9-

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for NEELKANTHDHARA, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000011078402/10/2019PRATIK MUKESH MODI vs SHANTILAL VELJISENGHANIorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 20223. Presently, about 95% to 98% of Works are completed. But in view of outbreak of a pandemic COVID-19, it may take further time beyond 30/06/2021 for completion of 100% works. More
30 Jun 202230 Dec 2025about 95% to 98% of Works are completed. But in view of outbreak of a pandemic COVID-19, it may take further time beyond 30/12/2022for completion of 100% works. Moreover as the pro

Location, Land & Connectivity

Located at GHATKOPAR WEST, L B S ROAD, Kurla, Mumbai Suburban, 400086. Per the filed land record, the plot is bounded to the north by NALA, to the south by CTS NO 375, to the east by NALA and to the west by CTS NO 395. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Powai / Hiranandani business park3 km
Chhatrapati Shivaji Int'l Airport4 km
Bandra Kurla Complex (BKC)5 km
Andheri MIDC / SEEPZ6 km
Lower Parel / Worli business district13 km
Nariman Point / Fort20 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Ashapura Developers is the promoter on 5 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

See every Ashapura Developers project & its RERA track record →

Other flagged projects by Ashapura Developers

Ashapura Developers
FlaggedMumbai Suburban

Other RERA-registered projects in Ghatkopar West

O AND S Royale
possession by Dec 2026 · Suchita Orange Project Royale
Sarvonnati CHS LTD
Deregistered by MahaRERA · possession by Dec 2026 · JAI Enterprises
Vighneshwar Cooperative Housing Society Limited
possession by Dec 2026 · Vighneshwar Coop Housing Society Limited
Arihant Heights
possession by Dec 2026 · Arihant Infrastructure Company
Avani Signature
possession by Dec 2026 · Avani Buildcon
Sanghvi Parsssva Jivdaya
possession by Dec 2026 · Sanghvi Constructions

Other RERA-registered projects in Mumbai Suburban

Neelrekha
declared completion Dec 2019 · Tasmai Spaces
Neelyog Aarana
possession by Jun 2028 · Neelyog Builders Private Limited
Neelyog Aashiyana II
declared completion Jun 2026 · Neelyog Construction Pvt Ltd
Neelyog Regent
possession by Mar 2028 · Ratan Builders
Neelyog Virat -A Wing
possession by Dec 2026 · Neelyog Construction Pvt Ltd
Neera Enclave
declared completion Mar 2026 · Shraddha Divine Realtors LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026