Plotted Development Intelligence · Raigarh

NERAL HEIGHTS

P52000012561 · promoter Siddhidhata Developers

Certificate SignedDue 31 Jul 2018

Delivery & Registration

MahaRERA registrationP52000012561
Registered on04 Sep 2017
Promoter-declared completion31 Jul 2018
Current statusCertificate Signed
Against todayabout 96 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Siddhidhata Developers is the promoter of record on 5 projects, of which 3 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Borivali, Mumbai Suburban, 410101. Per the filed land record, the plot is bounded to the north by SURVEY NO 69 PART 1 AND 69 PART 2B AND 55 AND 54, to the south by BY SURVEY NO 69 PART 5, to the east by BY BOUNDARY OF VILLAGE KUMBHE and to the west by SURVEY NO 55 AND 57. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~47 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park47 km
Bandra Kurla Complex (BKC)50 km
Chhatrapati Shivaji Int'l Airport50 km
Andheri MIDC / SEEPZ51 km
Lower Parel / Worli business district53 km
Nariman Point / Fort55 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Neral

SAI Krupa Valley- Phase 1
possession by Aug 2026 · SAI Krupa Developers
Noble Apartment
possession by Aug 2026 · Asra Reality
Madina Complex
possession by Aug 2026 · Al-Hamd Developers
Arsh Apartment
possession by Sep 2026 · Mateen Rafique Patel
Naaz Plaza
possession by Sep 2026 · Prestige Reality
Aliza Apartments
possession by Dec 2026 · M/S SKY Homes

Major developers building in Neral

Other RERA-registered projects in Raigarh

Nest 1 Phase 2
declared completion Sep 2019 · Rajesh Virendra Gupta
Nest 2 Phase 2
declared completion Sep 2018 · Rajesh Virendra Gupta
Nestor
declared completion Mar 2025 · Kalpana Struct-CON Infra LLP
Netravati
declared completion Jun 2023 · Morajkar Estates LLP
New Gulmohar Co - Operative Housing Society
declared completion Dec 2025 · Pratham Infra
NEW Jadhav Apartment
possession by Mar 2027 · Riddhi Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026