Mumbai/Project record

MahaRERA · the public record

NERAL HEIGHTS

Mumbai Suburban · SIDDHIDHATA DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Jul 2018declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Jul 2018

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000012561

Delivery and registration

When is the project declared for completion?

NERAL HEIGHTS is registered with MahaRERA as P52000012561 and the promoter has declared completion for 31 Jul 2018.

31 Jul 2018

declared completion

98months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000012561
Registered on04 Sep 2017
Promoter-declared completion31 Jul 2018
Current statusCertificate Signed
Against todayabout 98 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for NERAL HEIGHTS record 5 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 5 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Siddhidhata Developers is the promoter of record on 5 projects registered with MahaRERA, 3 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

5projects

registered with MahaRERA

3flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

How much has actually been sold?

In NERAL HEIGHTS, 36 of 48 plots filed with MahaRERA are recorded as sold or booked, about 75%, and 12 remain available.

75%sold

36 of 48 plots

Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for NERAL HEIGHTS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Borivali, Mumbai Suburban, 410101. Per the filed land record, the plot is bounded to the north by SURVEY NO 69 PART 1 AND 69 PART 2B AND 55 AND 54, to the south by BY SURVEY NO 69 PART 5, to the east by BY BOUNDARY OF VILLAGE KUMBHE and to the west by SURVEY NO 55 AND 57. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~47 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park47 km
Bandra Kurla Complex (BKC)50 km
Chhatrapati Shivaji Int'l Airport50 km
Andheri MIDC / SEEPZ51 km
Lower Parel / Worli business district53 km
Nariman Point / Fort55 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Neral

Arsh Apartment
possession by Sep 2026 · Mateen Rafique Patel
Naaz Plaza
possession by Sep 2026 · Prestige Reality
Labdhi Gardens Phase 6
possession by Dec 2026 · Labdhi Lifestyle Limited
Labdhi Gardens Phase 7
possession by Dec 2026 · Labdhi Lifestyle Limited
Labdhi Gardens Phase 8
possession by Dec 2026 · Labdhi Lifestyle Limited
RAJ Baug Phase - III
possession by Dec 2026 · Nehaldhara Realtors

Major developers building in Neral

Other RERA-registered projects in Raigarh

Nest 1 Phase 2
declared completion Sep 2019 · Rajesh Virendra Gupta
Nest 2 Phase 2
declared completion Sep 2018 · Rajesh Virendra Gupta
Netravati
declared completion Jun 2023 · Morajkar Estates LLP
New Gulmohar Co - Operative Housing Society
declared completion Dec 2025 · Pratham Infra
NEW Jadhav Apartment
possession by Mar 2027 · Riddhi Developers
NEW Matheran
declared completion Sep 2024 · Wings Meyaar Realty Ventures LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026