NIVANT CHS LTD

P51800011747 · VILE PARLE WEST · promoter Constructions

Certificate SignedDue 29 Dec 2020

Delivery & Registration

MahaRERA registrationP51800011747
Registered on31 Aug 2017
Promoter-declared completion29 Dec 2020
Current statusCertificate Signed
Against todayabout 67 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+12.

BuildingWingsFloorsDeclared completion
NIVANT CHS LTD1G+12-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
29 Dec 202029 Jun 2020Project Nivant’s original proposed date of completion was 30th June 2019 at the time it’s registration with RERA on 31st July 2017. The revision in the original proposed date of co

Location, Land & Connectivity

Located at VILE PARLE WEST, BAJAJ ROAD, Andheri, Mumbai Suburban, 400056. Per the filed land record, the plot is bounded to the north by PLOT NO 45 BEARING CTS NO 899A, to the south by PLOT NO 39 BEARING CTS NO 900, to the east by PLOT NO 43 BEARING CTS NO44 and to the west by BAJAJ ROAD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~4 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Chhatrapati Shivaji Int'l Airport3 km
Andheri MIDC / SEEPZ4 km
Bandra Kurla Complex (BKC)5 km
Powai / Hiranandani business park7 km
Lower Parel / Worli business district12 km
Nariman Point / Fort20 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Vile Parle West

Navkar Residency
possession by Sep 2026 · OM Navkar Infrastructure LLP
Tulsidham CHS
possession by Sep 2026 · SM & Happy Home Associates
56 Park Avenue
possession by Dec 2026 · Krishang Infra Private Limited
Ajmera Shringaar
possession by Dec 2026 · H J Corporation
Durga Gayatri
possession by Dec 2026 · Manoj Mohanlal Goradia
Eden 62
possession by Dec 2026 · Ekta Nagpal Ventures LLP

Other RERA-registered projects in Mumbai Suburban

Nivetia Heights
possession by Jun 2027 · KBS Properties Pvt Ltd
NL Aryavarta
declared completion Mar 2019 · Nahalchand Laloochand Pvt. Ltd.
NL Park View
possession by May 2028 · Beautiful Properties Private Limited
NL Taksasila
declared completion Jun 2024 · Nahalchand Laloochand Pvt. Ltd.
Noble Height
declared completion Mar 2021 · Noble Construction
Noble Heights
declared completion Dec 2025 · Noble Infra Projects

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026