MahaRERA Property Intelligence · Mumbai Suburban

Ocean heights by Midcity Group

P51800008981 · promoter Midcity Heights

Certificate SignedDue 31 Dec 2023

Delivery & Registration

MahaRERA registrationP51800008981
Registered on19 Aug 2017
Promoter-declared completion31 Dec 2023
Current statusCertificate Signed
Against todayabout 31 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Midcity Heights is the promoter of record on 2 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+21.

BuildingWingsFloorsDeclared completion
Ocean Heights by Midcity Group1G+2131 Dec 2019

Complaints & Orders

11 complaints are on the MahaRERA record for this project, with orders passed in 5. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000019559411/01/2021Amit Haresh Wadhwani vs M/s. Mid City Heightspending / no order on file
CC00600000028212528/07/2022VAIBHAV VISHANT vs Midcity Heights Pvt Ltdorder passed
CC00600000036475713/03/2023Zuber Abdul Hamid Kazi vs M/s Midcity Heightsorder passed
CC00600000039733209/09/2023Sandeep Jindal vs M/s Midcity Heightsorder passed
CC1240002604/09/2024FARHAN IQBAL KHAN vs M/s Midcity Heightsorder passed
CC1250322512/09/2025Arun Kumar Sharma vs M/s Midcity Heightspending / no order on file
CC1260075009/02/2026Sanjey Bajoria vs M/s Midcity Heightspending / no order on file
CC1260093920/02/2026Milan Sonigra vs M/s Midcity Heightspending / no order on file
CC1260137012/03/2026Vijay Raosaheb Patil vs M/s Midcity Heightspending / no order on file
CC1260137312/03/2026Supriya Harshwardhan Hukkeri vs M/s Midcity Heightspending / no order on file
CC1260283814/05/2026Shreyas Prakash Yande vs M/s Midcity Heightsorder passed

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Dec 202330 Jun 2021Delay due to change in DPDCR policy. Had to apply for CRZ and Forest Department NOC.
31 Dec 202331 Dec 2023DUE TO ONGOING PANDEMIC AND THE SHORTAGE OF LABOUR, THE PROMOTER COULD NOT COMPLETE THE PROJECT WITHIN THE TIME. THEREFORE EXTENSION UNDER SECTION 7(3) OF RERA HAS BEEN SOUGHT BY

Location, Land & Connectivity

Located at Andheri, Mumbai Suburban, 400102. Per the filed land record, the plot is bounded to the north by Sub-Plot No 2, to the south by Sky Heaven, to the east by 13 meter wide road and to the west by Sub Plot No 1. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~4 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Andheri MIDC / SEEPZ4 km
Chhatrapati Shivaji Int'l Airport7 km
Powai / Hiranandani business park8 km
Bandra Kurla Complex (BKC)9 km
Lower Parel / Worli business district16 km
Nariman Point / Fort24 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Jogeshwari West

Aksa Tower
possession by Sep 2026 · HFI Industries
GSA Grandeur
Past its declared completion date · possession by Oct 2026 · G S A Constructions
Lashkaria Pearl
possession by Nov 2026 · Lashkaria Housing & Infrastructure P
A H Avenue
possession by Dec 2026 · A.h. Constructions
KEY Tech Park
possession by Dec 2026 · M/s Keytech
Universal Garden- B Wing
possession by Dec 2026 · Pagarani Universal Infrastructure Pvt Lt

Major developers building in Jogeshwari West

Other RERA-registered projects in Mumbai Suburban

Ocean View
possession by Dec 2026 · Star Construction
Oceanic
possession by Dec 2030 · Oberoi Realty Limited
ODC 1
declared completion Jul 2026 · NVN Buildcon LLP
Odhav Baug
declared completion Sep 2018 · S. K. Construction
Odhav K K Residency
possession by Mar 2028 · K. K. Patel & Sons
Odina
declared completion Sep 2020 · Rajyog Enterprise

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.