MahaRERA Property Intelligence · Raigarh
P52000014181 · Neral · promoter Priztine Infra Llp
| MahaRERA registration | P52000014181 |
| Registered on | 13 Nov 2017 |
| Promoter-declared completion | 31 Dec 2027 |
| Current status | Certificate Signed |
| Against today | 17 months to the declared date |
MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.
MahaRERA's cost filing puts construction at ~36.5% of the estimated project cost incurred as of the last certificate (₹11.43 Cr spent against a ₹31.31 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows.
Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.
Of 812 homes filed with MahaRERA, 291 are sold/booked (261 with registered agreements + 30 booked) and 521 remain available (~36% sold) — early in sales — more choice of units now, but confirm the developer has the pre-sales to fund the build. Buyers have committed ₹30.30 Cr in agreement value so far. Of that, ₹20.63 Cr (~68%) is already collected, ₹9.68 Cr receivable — a read on how far along these sales really are. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.
What buyers actually paid: across 291 registered agreements, the effective carpet rate is ₹4,750/sqft (typical range ₹3,914–₹5,482) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.
No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4 and 812 homes are registered across the project.
| Building | Wings | Floors | Homes | Declared completion |
|---|---|---|---|---|
| A1 | 1 | G+4 | 50 | - |
| A2 | 1 | G+4 | 50 | - |
| A3 | 1 | G+4 | 50 | - |
| A4 | 1 | G+4 | 50 | - |
| A5 | 1 | G+4 | 50 | - |
| A6 | 1 | G+4 | 50 | - |
| A7 | 1 | G+4 | 50 | - |
| A8 | 1 | G+4 | 50 | - |
| B1 | 1 | G+4 | 55 | - |
| B2 | 1 | G+4 | 55 | - |
| B3 | 1 | G+4 | 55 | - |
| B4 | 1 | G+4 | 55 | - |
| B5 | 1 | G+4 | 55 | - |
| B6 | 1 | G+4 | 55 | - |
| B7 | 1 | G+4 | 55 | - |
| Commercial Plaza | 1 | G+1 | 27 | - |
Unit mix on the filing: 785 residential and 27 non-residential (shops/offices).
6 complaints are on the MahaRERA record for this project, with orders passed in 4. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.
| Complaint no. | Filed | Parties | Status |
|---|---|---|---|
| CC006000000396055 | 03/06/2023 | SANJAY SADASHIV SOLIM vs PRIZTINE INFRA LLP | order passed |
| CC12502721 | 04/08/2025 | Mahtab Khurshid Shaikh vs PRIZTINE INFRA LLP | order passed |
| CC12502889 | 17/08/2025 | Amar Dhurandhar vs PRIZTINE INFRA LLP | order passed |
| CC12503877 | 05/11/2025 | Jaimini Sarkar vs PRIZTINE INFRA LLP | order passed |
| CC12600426 | 23/01/2026 | Mayur Shivaji Jadhav vs PRIZTINE INFRA LLP | pending / no order on file |
| CC12600428 | 23/01/2026 | SANDESH PANDURANG KANAL vs PRIZTINE INFRA LLP | pending / no order on file |
The promoter has had the MahaRERA completion deadline formally extended 3 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.
| From (declared) | To (revised) | Stated reason |
|---|---|---|
| 30 Dec 2022 | 30 Dec 2023 | The project is under construction with Civil and Infrastructure work in progress, with 2 buildings (Building A8 & Building A5) complete and ready for possession, but progress of re |
| 30 Dec 2022 | 30 Dec 2024 | The project is under construction with Civil and Infrastructure work in progress, with 3 buildings (Building A8, Building A4 & Building A5) complete and ready for possession, but p |
| 30 Dec 2022 | 31 Dec 2027 | The project is under construction with civil and infrastructure work in progress. Three buildings (A8, A4 & A5) are completed and ready for possession. However, the project is yet |
Located at Neral, Maniwali, Panvel, Raigarh, 410101. Per the filed land record, the plot is bounded to the north by Manivali Village, to the south by Avsare Village, to the east by ZP Road and to the west by Mohili Village. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.
The nearest major job hub is ~46 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.
| Landmark | Straight-line |
|---|---|
| Powai / Hiranandani business park | 46 km |
| Bandra Kurla Complex (BKC) | 49 km |
| Andheri MIDC / SEEPZ | 49 km |
| Chhatrapati Shivaji Int'l Airport | 50 km |
| Lower Parel / Worli business district | 54 km |
| Nariman Point / Fort | 56 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.
🔒 The verdict & buyer playbook · Compliance report
The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.
🔒 Unit-by-unit guidance · Unit Guidance report
Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.
🔒 Full financial records — escrow, funding & the document catalog · Compliance report
The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.
Should you buy in Olympeo Neo City?
This page is the free MahaRERA filing summary. The full RERA Property Intelligence Report gives you the full regulatory standing, declared court litigation, buyer-complaint and adjudication history, quarterly-progress-report discipline, the builder's MahaRERA-wide track record, the building/tower breakdown, and the sanctioned layout plan. See a real one first:
Sample: Lodha Kandivali – Tower 2 → · browse all sample reports →
Compliance Report · ₹999
The regulator’s filing record, read · 1 working day
Scan with any UPI app to pay · quietlist@kotak
Unit Guidance Report · ₹2,999
Everything, down to which unit · 1 working day
Not useful to your decision? Full refund — no questions asked.
Scan with any UPI app to pay · quietlist@kotak
Paying from outside India? Pay $15 (Compliance) or $39 (Unit Guidance) via PayPal, or email hello@quietlist.in for a card invoice. Prefer to talk first, or have a portfolio to check? Same address. An information aid for your own due diligence, not legal or investment advice.
Free · Watch this project
We'll email you when this project's RERA record changes.
Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.
Last checked against the RERA register: 27 Jul 2026