MahaRERA Property Intelligence · Raigarh

OM RESIDENCY

P52000016319 · PANVEL · promoter Om Builder And

Certificate SignedDue 31 Mar 2019

Delivery & Registration

MahaRERA registrationP52000016319
Registered on03 May 2018
Promoter-declared completion31 Mar 2019
Current statusCertificate Signed
Against todayabout 88 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+3.

BuildingWingsFloorsDeclared completion
OM RESIDENCY1G+331 Mar 2019

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at PANVEL, NEAR PANVEL MATHERAN ROAD, Panvel, Raigarh, 410210. Per the filed land record, the plot is bounded to the north by GUT NO 85, to the south by ROAD AREA, to the east by PLOT NO 3 and to the west by OPEN SPACE. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~28 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park28 km
Bandra Kurla Complex (BKC)29 km
Chhatrapati Shivaji Int'l Airport30 km
Andheri MIDC / SEEPZ32 km
Lower Parel / Worli business district33 km
Nariman Point / Fort35 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kharghar

Tharwani Palladian
possession by Sep 2026 · Tharwani Realtors
Balaji Park
possession by Oct 2026 · Mohansingh Tararam Choudhary
Krishna Aura
possession by Oct 2026 · Qualitas Lifespaces LLP
Shree Darshan
possession by Dec 2026 · Hari OM Developers
7 OAK Apaprtment
possession by Dec 2026 · Takhatsinh Pravinsinh Rana
Ashwini Apartment
possession by Dec 2026 · Kuldeepsingh Amarsingh Bhalothia

Major developers building in Kharghar

Other RERA-registered projects in Raigarh

OM Residency
possession by Mar 2029 · Rajkumar Trimbak Karad
OM Rudra Heights
declared completion Dec 2023 · Rudra Realtors
Om Sadashiv
possession by Jun 2027 · Om Builders And Developers
OM SAI
declared completion May 2026 · Suresh Kashinath More
OM SAI Aangan
declared completion Apr 2026 · Hanuman Sopan Gaikwad
OM SAI Apartment
declared completion May 2024 · OM SAI Builders & Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026