Mumbai/Project record

MahaRERA · the public record

OM SUNKULAN

MAKANE · VIDHI ENTERPRISES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

72units filed as unsoldInventory · 19 September 2026
31 Dec 2028declared completionMahaRERA registration · read 12 Jul 2026
121registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2028

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000055942

Delivery and registration

When is the project declared for completion?

OM SUNKULAN is registered with MahaRERA as P99000055942 and the promoter has declared completion for 31 Dec 2028.

31 Dec 2028

declared completion

27months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000055942
Registered on02 May 2024
Promoter-declared completion31 Dec 2028
Current statusCertificate Signed
Against today27 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for OM SUNKULAN record 12 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Vidhi Enterprises is the promoter of record on 9 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

9projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Construction

How much construction cost has been reported?

In OM SUNKULAN, ₹4.39 Cr of a declared ₹19.31 Cr estimated project cost is reported as incurred, about 22.7%, as at the last certified filing with MahaRERA.

22.7%

₹4.39 Cr

of ₹19.31 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In OM SUNKULAN, 0 of 72 homes filed with MahaRERA are recorded as sold or booked, about 0%, and 72 remain available.

0%sold

0 of 72 homes

Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. The project registers 121 homes in total, while this sold/unsold inventory filing covers 72 of them.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

The inventory filing also declares: 49 owner/investor-held.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for OM SUNKULAN in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 19 September 2026

What the filings record, home by home

Read from MahaRERA on 19 September 2026

No home in OM SUNKULAN carries a registered agreement value on its MahaRERA filing, so there is no record here of what anyone has paid. What the promoter has filed is the government ready reckoner value for 121 homes — the Annual Statement of Rates valuation, with each home’s carpet area and floor already applied. Across them that is Rs 3,499 a sq ft typical, over Rs 3,499 to Rs 3,499.

A reckoner value is the basis stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home to you.

The Reckoner Record lists all 121 of them — each home, its RERA carpet area, the valuation filed against it and the rate that works out to. It is the filing copied, not a reading of it.

See all 121 filed valuations — ₹999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7 and 121 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
BUILDING NO 11G+731-
BUILDING NO 21G+731-
BUILDING NO 31G+759-

Unit mix on the filing: 121 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at MAKANE, MAKANE, Palghar, Palghar, 401102. Per the filed land record, the plot is bounded to the north by ROAD, to the south by BUILDING, to the east by BUILDING and to the west by ROAD. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Vidhi Enterprises is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Vidhi Enterprises

Other RERA-registered projects in Makane

Excellence Residency 3
possession by Dec 2026 · SAI Excellence Developers
Nayan-Vastu Heritage
Not filing quarterly progress reports · possession by Dec 2026 · Unity Infra
Nayan-Vastu Heritage
possession by Dec 2026 · Unity Infra
Nine Star Prestige Building NO. 1
possession by Dec 2026 · Nine Home Creators
Nine Star Prestige Building NO. 2
possession by Dec 2026 · Nine Home Creators
Ninestar Crown Bldg NO 5 Emerald
possession by Dec 2026 · Nine Homemakers

Other RERA-registered projects in Palghar

OM Vighnaharta Tower
declared completion Dec 2025 · OM Vighnaharta Developers
Omkar Apartment
declared completion May 2024 · OM Builders AND Developers
Omkar Apartment
declared completion Dec 2023 · Ravindra Rajesh Kanna
Omkar Palace
declared completion Sep 2021 · Neelam Builders
Omkar Residency
possession by Jul 2028 · Omkar Builders And Developers
Omkar Vastu Complex
possession by Dec 2026 · Omkar Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026