MahaRERA Property Intelligence · Palghar

Orchid-Hans Heritage

P99000023222 · Arvind Park Boisar West · promoter Hans Realtors

Certificate SignedDue 31 Jul 2023

Delivery & Registration

MahaRERA registrationP99000023222
Registered on06 Dec 2019
Promoter-declared completion31 Jul 2023
Current statusCertificate Signed
Against todayabout 36 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Hans Realtors is the promoter of record on 102 projects, of which 13 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
Orchid1G+531 Jul 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Arvind Park Boisar West, Tarapur Boisar Road , Palghar, Palghar, 401502. Per the filed land record, the plot is bounded to the north by Building No 5, to the south by Open Space, to the east by Building No 4 and to the west by Existing Road. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~140 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park140 km
Andheri MIDC / SEEPZ141 km
Chhatrapati Shivaji Int'l Airport145 km
Bandra Kurla Complex (BKC)147 km
Lower Parel / Worli business district156 km
Nariman Point / Fort163 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kurgaon

Aakash Complex
possession by Nov 2026 · Lxmi Infra
Nisarg -Building No.2
possession by Dec 2026 · Agora Life Space
Solitaire Height
possession by Dec 2026 · Affak Arif Motiwala
Whitehill Residential
possession by Dec 2026 · Riva Realtors
Bhakti Avenue
possession by Mar 2027 · Bhakti Green Realty LLP
Aster Hans Heritage
possession by Sep 2028 · Hans Realtors

Other RERA-registered projects in Palghar

Orchid Hill Fronts
declared completion Dec 2019 · Shrushti Developers
Orchid-I
declared completion Dec 2025 · JAY Enterprise
Orchid - II
possession by Dec 2026 · JAY Enterprise
Orchid Plaza
possession by Dec 2029 · K V Infra
Orchid Villas
possession by Dec 2030 · Sharp Developers
Ornate Galaxy Phase I
declared completion Oct 2020 · Sai Ornate Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026