Mumbai/Project record

MahaRERA · the public record

ORNATE GALAXY PHASE II

VASAI · Sai Ornate Developers

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000028425

Delivery and registration

When is the project declared for completion?

ORNATE GALAXY PHASE II is registered with MahaRERA as P99000028425 and the promoter has declared completion for 30 Dec 2023.

30 Dec 2023

declared completion

33months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000028425
Registered on02 Mar 2021
Promoter-declared completion30 Dec 2023
Current statusCertificate Signed
Against todayabout 33 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for ORNATE GALAXY PHASE II record 12 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 12 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Sai Ornate Developers is the promoter of record on 13 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

13projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for ORNATE GALAXY PHASE II in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
C AND D WING 12 TO 14 FLOORS1G+430 Jun 2023

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for ORNATE GALAXY PHASE II, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC1240118620/12/2024Sunil Gupta vs Ajay Kumar Pravinlal Shahorder passed

Location, Land & Connectivity

Located at VASAI, VILLAGE JUCHANDRA , Andheri, Mumbai Suburban, 401202. Per the filed land record, the plot is bounded to the north by ROAD SIDE, to the south by SURVEY NO 331 PT, to the east by SURVEY NO 352 HISSA NO 2 AND 4 and to the west by SURVEY NO 352 HISSA NO 1. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Sai Ornate Developers is the promoter on 2 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other RERA-registered projects in Vasai West

Happy Home Jasmine C D
possession by Sep 2026 · Happy Home Corporation
Dream Aura
possession by Dec 2026 · Clement Regency Developers
Vijaya Complex
Not filing quarterly progress reports · possession by Dec 2026 · Padmavati Enterprises
Ashoka Heavens
possession by Dec 2026 · Shree Mahashraman Realtors
Dattani Vertex Building No.4 Wing EF
possession by Dec 2026 · Brijesh Satish Dattani
Gokarna Residency
possession by Dec 2026 · Harshal Anil Acharya

Other RERA-registered projects in Palghar

Ornate Heights Phase II
possession by Jun 2027 · Ornate City Developers
Ornate Serenity
possession by Mar 2028 · SAI Ornate Developers
Oscar Valley
declared completion Jun 2025 · M/s. Tricolour Properties Pvt. Ltd.
Osian Royale
declared completion Jul 2026 · Eskcays Estatess Private Limited
Osian Royale
possession by Mar 2030 · Eskcays Estatess Private Limited
Ostwal Dream Land
declared completion Dec 2019 · Shree Ostwal Builders LTD

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026