OSSIA ENCLAVE

Eksar road · R B Developers

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

4units filed as unsoldInventory · 13 September 2026
31 Mar 2027declared completionMahaRERA registration · read 12 Jul 2026
24registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Mar 2027

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800005753

Delivery and registration

When is the project declared for completion?

OSSIA ENCLAVE is registered with MahaRERA as P51800005753 and the promoter has declared completion for 31 Mar 2027.

31 Mar 2027

declared completion

6months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800005753
Registered on11 Aug 2017
Promoter-declared completion31 Mar 2027
Current statusCertificate Signed
Against today6 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for OSSIA ENCLAVE record 35 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 35 quarterly progress reports on record since registration, with no current default.

Construction

How much construction cost has been reported?

In OSSIA ENCLAVE, ₹8.37 Cr of a declared ₹8.78 Cr estimated project cost is reported as incurred, about 95.3%, as at the last certified filing with MahaRERA.

95.3%

₹8.37 Cr

of ₹8.78 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In OSSIA ENCLAVE, 9 of 13 homes filed with MahaRERA are recorded as sold or booked, about 69%, and 4 remain available.

69%sold

9 of 13 homes

₹8.48 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹8.48 Cr (about 100%) is recorded as collected and ₹0 as receivable. The project registers 24 homes in total, while this sold/unsold inventory filing covers 13 of them.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 9 registered agreements, the effective carpet rate is ₹15,004/sqft, with eight in ten falling between ₹13,223 and ₹16,932 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

The units recorded as unsold on the filing. The reckoner value is the government's ready-reckoner assessment the promoter filed against that unit, the figure stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home.

FloorUnitCarpetGovt reckoner value
Floor 5502613 sqft (56.91 sqm)₹98.48 Lakh
Floor 6601726 sqft (67.49 sqm)₹1.17 Cr
Floor 6603432 sqft (40.16 sqm)₹69.49 Lakh
Floor 7701402 sqft (37.38 sqm)₹64.68 Lakh

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

What the filings record, home by home

Read from MahaRERA on 13 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 9 homes carry one, and 4 of the 13 are recorded unsold.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
601726 sqftRs 1.0900 cr typical, over Rs 1.0900 cr to Rs 1.2300 cr4 filed on this stack, floors 2–5

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.

In OSSIA ENCLAVE, 1 of the 4 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 3 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+27 and 24 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
OSSIA ENCLAVE1G+272430 Jun 2018

Unit mix on the filing: 24 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 4 times, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 2020AREA CORRECTION ON PROPERTY CARD
30 Jun 202030 Jun 2020Area correction on PR card is in progress at collector office and city survey office.
30 Jun 202031 Dec 2021Society has applied for said land on a lease basis & the application is pending from Revenue Minister, Revenue & Forest Department.
31 Dec 202131 Mar 20271) Lease Formalities of Collector’s Land Portion A portion of the subject land falls under land administered by the Collector. The Society has obtained the said portion on lease fr

Location, Land & Connectivity

Located at Eksar road, CKP colony, Borivali, Mumbai Suburban, 400092. Per the filed land record, the plot is bounded to the north by SLUM AREA, to the south by PRIYESH CHSL, to the east by JYOTI CHSL and to the west by NEW SHARYU CHSL. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~12 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Andheri MIDC / SEEPZ12 km
Powai / Hiranandani business park14 km
Chhatrapati Shivaji Int'l Airport16 km
Bandra Kurla Complex (BKC)19 km
Lower Parel / Worli business district26 km
Nariman Point / Fort34 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Borivali West

Gopal Terrace Co-Operative Housing Society LTD
possession by Sep 2026 · Polo Infra Developers Private Limited
House Of Shreeji Sharan
possession by Sep 2026 · Miles Infra LLP
Sai Signature Spaces
possession by Sep 2026 · Ramachandran Munisawmy Narayan
Shikhhar
possession by Sep 2026 · Mahavir Land Developer
Swastik
possession by Sep 2026 · Reliance Corporation
Signet
possession by Oct 2026 · DG Builders

Major developers building in Borivali West

Other RERA-registered projects in Mumbai Suburban

Ostwal Fermino
possession by Dec 2030 · Shree Ostwal Builders LTD
Ostwal Gala Kunj
possession by Dec 2029 · Shree Ostwal Builders LTD
Oswal Avenue
possession by Dec 2026 · Diwaliben Champshi Shah
OUR Home Chsl
possession by May 2030 · Namo Realty Ventures LLP
Ozone Avenue
possession by Jun 2030 · Blue Line Infra Developers
Ozone Heritage
possession by Jun 2028 · Blue Ocean Realty

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.