PARAMOUNT ENCLAVE PHASE 2, BLDG NO 1, TYPE D

PALGHAR · SHREE GAJANAND HOMES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

29 Jun 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

29 Jun 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000026806

Delivery and registration

When is the project declared for completion?

PARAMOUNT ENCLAVE PHASE 2, BLDG NO 1, TYPE D is registered with MahaRERA as P99000026806 and the promoter has declared completion for 29 Jun 2024.

29 Jun 2024

declared completion

27months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000026806
Registered on25 Oct 2020
Promoter-declared completion29 Jun 2024
Current statusCertificate Signed
Against todayabout 27 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for PARAMOUNT ENCLAVE PHASE 2, BLDG NO 1, TYPE D record 15 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 15 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Shree Gajanand Homes is the promoter of record on 7 projects registered with MahaRERA, 3 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

7projects

registered with MahaRERA

3flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for PARAMOUNT ENCLAVE PHASE 2, BLDG NO 1, TYPE D in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
PARAMOUNT ENCLAVE PHASE 2, BLDG NO 1, TYPE D1G+531 Dec 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered29 Jun 2024DEAR SIR, DUE TO GLOBAL PENDAMIC COVID 19 THE BUSINESS HAS BEEN SUFFERED AND REQUIRED MORE TIME TO COMPELTE THE PROJECT AND OBTAIN THE O.C. THUS KINDLY PROVIDE US FURTHER EXTENS

Location, Land & Connectivity

Located at PALGHAR, MAHIM ROAD, Vasai, Palghar, 400066. Per the filed land record, the plot is bounded to the north by 18 METER WIDE ROAD, to the south by PROPOSED BUILDING, to the east by PROPOSED BUILDING and to the west by PROPOSED BUILDING. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~288 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park288 km
Andheri MIDC / SEEPZ289 km
Chhatrapati Shivaji Int'l Airport293 km
Bandra Kurla Complex (BKC)294 km
Lower Parel / Worli business district302 km
Nariman Point / Fort308 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Borivali East

Proposed Redevelopment OF Prakashkunj Chsl
possession by Sep 2026 · Yash Realtors & Developers
Chandratej CHS LTD
possession by Oct 2026 · Elesh Ravjibhai Rathod
Eknath Gruh
possession by Oct 2026 · Vastav Developers PVT LTD
NEW Avanti Chsl
possession by Oct 2026 · Balaji Enterprises
Empire Vrindavan
possession by Nov 2026 · Empire Realty
66 Avenue
possession by Dec 2026 · Parsh Realtors

Major developers building in Borivali East

Other RERA-registered projects in Palghar

Paramount Enclave Phase II Building NO. 3 B Wing
declared completion Jun 2026 · Shree Balaji Infra
Paramount Enclave, Phase-II, Building No 3, Wing-A, Type-C
possession by Jun 2027 · Brajbhoomi Developers
Paramount Height
possession by Dec 2027 · Munish Group OF Company
Parashakti Apartment
declared completion Dec 2023 · Hiralal Arjunlal Chaudhary
Parasnath Corner
declared completion Mar 2026 · Shreenath Enterprises
Parasnath Garden-S NO 182-3 196-7
possession by Sep 2027 · Shreenath Enterprises

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.