MahaRERA Property Intelligence · Palghar

PARAMOUNT ENCLAVE PHASE 2, BLDG NO 1, TYPE D

P99000026806 · PALGHAR · promoter Shree Gajanand Homes

Certificate SignedDue 29 Jun 2024

Delivery & Registration

MahaRERA registrationP99000026806
Registered on25 Oct 2020
Promoter-declared completion29 Jun 2024
Current statusCertificate Signed
Against todayabout 25 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Shree Gajanand Homes is the promoter of record on 6 projects, of which 3 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
PARAMOUNT ENCLAVE PHASE 2, BLDG NO 1, TYPE D1G+531 Dec 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Jun 202329 Jun 2024DEAR SIR, DUE TO GLOBAL PENDAMIC COVID 19 THE BUSINESS HAS BEEN SUFFERED AND REQUIRED MORE TIME TO COMPELTE THE PROJECT AND OBTAIN THE O.C. THUS KINDLY PROVIDE US FURTHER EXTENS

Location, Land & Connectivity

Located at PALGHAR, MAHIM ROAD, Vasai, Palghar, 400066. Per the filed land record, the plot is bounded to the north by 18 METER WIDE ROAD, to the south by PROPOSED BUILDING, to the east by PROPOSED BUILDING and to the west by PROPOSED BUILDING. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~288 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park288 km
Andheri MIDC / SEEPZ289 km
Chhatrapati Shivaji Int'l Airport293 km
Bandra Kurla Complex (BKC)294 km
Lower Parel / Worli business district302 km
Nariman Point / Fort308 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Borivali East

Rushabh Apartment
possession by Jul 2026 · R R Builders
Rashmi Manorath
possession by Aug 2026 · Modi's Navnirman Limited
Proposed Redevelopment OF Prakashkunj Chsl
possession by Sep 2026 · Yash Realtors & Developers
Chandratej CHS LTD
possession by Oct 2026 · Elesh Ravjibhai Rathod
Eknath Gruh
possession by Oct 2026 · Vastav Developers PVT LTD
NEW Avanti Chsl
possession by Oct 2026 · Balaji Enterprises

Major developers building in Borivali East

Other RERA-registered projects in Palghar

Paramount Enclave Phase II Building NO. 3 B Wing
declared completion Jun 2026 · Shree Balaji Infra
Paramount Enclave, Phase-II, Building No 3, Wing-A, Type-C
possession by Jun 2027 · Brajbhoomi Developers
Paramount Height
possession by Dec 2027 · Munish Group OF Company
Paramount Heights
declared completion Jun 2023 · M/s Zion Constructions
Parashakti Apartment
declared completion Dec 2023 · Hiralal Arjunlal Chaudhary
Parasharam Pride
declared completion Nov 2023 · Durva Builders And Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026