Mumbai/Project record

MahaRERA · the public record

PARASNATH TOWNSHIP

PANCHALI GRAM PANCHAYAT · SHREENATH ENTERPRISES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

58units filed as unsoldInventory · 17 September 2026
31 Mar 2028declared completionMahaRERA registration · read 12 Jul 2026
193registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Mar 2028

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000015590

Delivery and registration

When is the project declared for completion?

PARASNATH TOWNSHIP is registered with MahaRERA as P99000015590 and the promoter has declared completion for 31 Mar 2028.

31 Mar 2028

declared completion

18months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000015590
Registered on08 Mar 2018
Promoter-declared completion31 Mar 2028
Current statusCertificate Signed
Against today18 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for PARASNATH TOWNSHIP record 35 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Shreenath Enterprises is the promoter of record on 66 projects registered with MahaRERA, 11 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

66projects

registered with MahaRERA

11flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Construction

How much construction cost has been reported?

In PARASNATH TOWNSHIP, ₹12.91 Cr of a declared ₹13.71 Cr estimated project cost is reported as incurred, about 94.2%, as at the last certified filing with MahaRERA.

94.2%

₹12.91 Cr

of ₹13.71 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In PARASNATH TOWNSHIP, 138 of 193 homes filed with MahaRERA are recorded as sold or booked, about 72%, and 55 remain available.

72%sold

138 of 193 homes

₹19.98 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹15.70 Cr (about 79%) is recorded as collected and ₹4.28 Cr as receivable.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 138 registered agreements, the effective carpet rate is ₹4,218/sqft, with eight in ten falling between ₹3,255 and ₹5,485 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

What the filings record, home by home

Read from MahaRERA on 17 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 135 homes carry one, and 58 of the 193 are recorded unsold. Since we started watching this ledger, 1 home has moved out of the unsold list, most recently on 08 September 2026.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
05161 sqftRs 5,427 a sq ft typical, over Rs 4,956 to Rs 5,4827 filed at this size

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. One of the two observations is an archived copy whose time is the moment the file was written, not a portal fetch time.

In PARASNATH TOWNSHIP, 37 of the 58 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 57 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7 and 193 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
PARASNATH TOWNSHIP BUILDING 11G+683-
PARASNATH TOWNSHIP BUILDING 21G+7110-

Unit mix on the filing: 130 residential and 63 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.

FromExtended toStated reason
as registered30 Mar 2021PROJECT GOT STUCK DUE TO FUND ISSUE THE LETTER OF BANK ATTACHMENT IS ATTACHED
30 Mar 202101 Mar 2025Due to lock down. and revised changes
01 Mar 202531 Mar 2028we need more time to complete the project, as slow response to project in terms of collection leaded us to extend the project date till 31/03/2028, we are fully dedicated to comple

Location, Land & Connectivity

Located at PANCHALI GRAM PANCHAYAT, PALGHAR BOISAR ROAD, Vasai, Palghar, 401404. Per the filed land record, the plot is bounded to the north by 387, to the south by 393 392, to the east by 388B 391 and to the west by 396 395. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~71 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ71 km
Powai / Hiranandani business park73 km
Chhatrapati Shivaji Int'l Airport76 km
Bandra Kurla Complex (BKC)78 km
Lower Parel / Worli business district86 km
Nariman Point / Fort93 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Shreenath Enterprises is the promoter on 12 MahaRERA-registered projects, of which 3 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Shreenath Enterprises project & its RERA track record →

Other flagged projects by Shreenath Enterprises

Shreenath Enterprises
FlaggedThane
Shreenath Enterprises
FlaggedPalghar
Shreenath Enterprises
FlaggedPalghar
Shreenath Enterprises
Not filing quarterly progress reportsPalghar
Shreenath Enterprises
Not filing quarterly progress reportsPalghar
Shreenath Enterprises
FlaggedPalghar

Other RERA-registered projects in Palghar

Parasnath Garden- SNO 200-1-2
possession by Sep 2026 · Shreenath Enterprises
SA Heights
possession by Sep 2026 · Atul Kumar Tripathi
SAI Park
possession by Sep 2026 · OM Siddhivinayak Developers
Shiv Krupa
possession by Oct 2026 · Shivaay Realty
V Square Arcade
possession by Oct 2026 · V Square
Nisarg Shrushti Phase-2
possession by Nov 2026 · Arvel Realtors

Major developers building in Palghar

Other RERA-registered projects in Palghar

Parasnath Township, Bldg-07, Wing-B, Type-G
possession by Dec 2028 · Shreenath Enterprises
Parijat Heights Building NO 3 Wing A
declared completion Jun 2026 · Viva Swastik Homes
Parivar Ashish Galaxy
possession by Jun 2029 · Parivar Ashish Developers
Parivar Complex Building NO 1 AND 3
possession by Jun 2030 · Parivar Homes
Parivar Complex Building NO 2
possession by Dec 2028 · Parivar Homes
Parivar D Wing
possession by Jun 2027 · Thdc Parivar LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026