Mumbai/Project record

MahaRERA · the public record

PARDESHI EMPIRE

TITWALA · VISHNU DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Mar 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Mar 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700034711

Delivery and registration

When is the project declared for completion?

PARDESHI EMPIRE is registered with MahaRERA as P51700034711 and the promoter has declared completion for 31 Mar 2025.

31 Mar 2025

declared completion

18months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700034711
Registered on20 Apr 2022
Promoter-declared completion31 Mar 2025
Current statusCertificate Signed
Against todayabout 18 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for PARDESHI EMPIRE record 12 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Filing progress reports — 12 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Vishnu Developers is the promoter of record on 81 projects registered with MahaRERA, 17 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

81projects

registered with MahaRERA

17flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for PARDESHI EMPIRE in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
PARDESHI EMPIRE1G+631 Mar 2024

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Mar 2025PROJECT HAS BEEN DELAYED DUE TO PROMOTER MEDICAL CONDITION

Location, Land & Connectivity

Located at TITWALA, HARI OM VALLEY ROAD, Kalyan, Thane, 421605. Per the filed land record, the plot is bounded to the north by ROAD, to the south by ROAD, to the east by BUNGLOW and to the west by 9 M W DP ROAD. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Vishnu Developers is the promoter on 3 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Vishnu Developers

Vishnu Developers
Past its declared completion dateThane

Other RERA-registered projects in Titwala

Ganpati Heights
possession by Sep 2026 · Manoj Prabhakar Patil
Indrayani
possession by Oct 2026 · Naresh Yashwant Patil
Mantra
possession by Nov 2026 · Vaidikh Nirmaan LLP
Rusttagi Aarambha 2.0
possession by Nov 2026 · Rustagi Estates Private Limited
Ganpati Prasanna
possession by Dec 2026 · Vijay Prabhakar Patil
Hillcrest Appartments
possession by Dec 2026 · Aasanghar Construction

Other RERA-registered projects in Thane

Pardeshi Paradise
declared completion Jul 2023 · Vishnu Developers
Parijas Horizon
possession by Jun 2028 · Octave Infraventures LLP
Parijatak Phase I A AND B Wing
declared completion Jun 2026 · Varad Builders
Parisparshs 23 Avenue
declared completion Mar 2026 · Parisparsh
Paritosh CO Operative Housing Society Limited
declared completion May 2026 · Not Available
Parivar Sadan CHS LTD
possession by Mar 2027 · Kaivalya AND Associates

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026