MahaRERA · the public record
PARDIS SHIVANSH
Chembur · PARDIS SHIVANSH LLP
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 12 Jul 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
31 Dec 2028
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
MahaRERA registration · read 12 Jul 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
MahaRERA · PR1180002500225
Delivery and registration
When is the project declared for completion?
PARDIS SHIVANSH is registered with MahaRERA as PR1180002500225 and the promoter has declared completion for 31 Dec 2028.
31 Dec 2028
declared completion
27months to go
against the declared date
The completion date and status as they stand on the MahaRERA registration record.
Source · MahaRERA project registration · read 12 Jul 2026
| MahaRERA registration | PR1180002500225 |
| Registered on | 07 Jul 2025 |
| Promoter-declared completion | 31 Dec 2028 |
| Current status | Certificate Signed |
| Against today | 27 months to the declared date |
Approvals and compliance
What compliance filings are on record?
MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for PARDIS SHIVANSH record 4 quarterly progress reports since registration.
4quarterly filings
Entries as they appear on MahaRERA's own lists and the project's progress filing.
Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026
- Filing progress reports — 4 quarterly progress reports on record since registration, with no current default.
Promoter record
What else is this promoter on record for?
Pardis Shivansh Llp is the promoter of record on 12 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).
12projects
registered with MahaRERA
0flagged
by MahaRERA
Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.
Source · MahaRERA register, all projects · read 12 Jul 2026
Construction
How much construction cost has been reported?
In PARDIS SHIVANSH, ₹2.32 Cr of a declared ₹12.50 Cr estimated project cost is reported as incurred, about 18.5%, as at the last certified filing with MahaRERA.
18.5%
₹2.32 Cr
of ₹12.50 Cr declared cost
Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.
Source · MahaRERA quarterly progress filing · read 12 Jul 2026
Sales
Are registered sale-agreement prices available?
No registered sale-agreement price is recorded for PARDIS SHIVANSH in the MahaRERA project file.
Not available
This is what the record does not contain, not a value of zero.
Source · MahaRERA project file · checked 12 Jul 2026
Buildings & Wings
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+0.
| Building | Wings | Floors | Declared completion |
|---|---|---|---|
| Building 1 | 1 | G+0 | - |
Complaints
No buyer complaints were on this project's MahaRERA record at the time of reading.
Legal & Litigation
The promoter has declared 1 court case on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.
| Court | Case no. | Year | Status |
|---|---|---|---|
| Revenue And Forest Department | 6040 | 2024 | Ongoing |
Location, Land & Connectivity
Located at Chembur, Road, Kurla, Mumbai Suburban, 400024. Per the filed land record, the plot is bounded to the north by PLOT NO 16, to the south by ROAD, to the east by PLOT NO 17 and to the west by PLOT NO 15. These are the boundaries as recorded in the filed land record.
Location & connectivity
The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.
| Landmark | Straight-line |
|---|---|
| Bandra Kurla Complex (BKC) | 3 km |
| Chhatrapati Shivaji Int'l Airport | 5 km |
| Powai / Hiranandani business park | 6 km |
| Andheri MIDC / SEEPZ | 8 km |
| Lower Parel / Worli business district | 10 km |
| Nariman Point / Fort | 17 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.