Parmarth Niketan - Redevelopment of Mani Bhuvan

Daulat Nagar · J V Constructions & Developers

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jun 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800001745

Delivery and registration

When is the project declared for completion?

Parmarth Niketan - Redevelopment of Mani Bhuvan is registered with MahaRERA as P51800001745 and the promoter has declared completion for 30 Jun 2023.

30 Jun 2023

declared completion

39months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800001745
Registered on29 Jul 2017
Promoter-declared completion30 Jun 2023
Current statusCertificate Signed
Against todayabout 39 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Parmarth Niketan - Redevelopment of Mani Bhuvan record 24 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 24 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Constructions Developers is the promoter of record on 51 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

51projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Parmarth Niketan - Redevelopment of Mani Bhuvan in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+14.

BuildingWingsFloorsDeclared completion
Parmarth Niketan - Redevelopment of Mani Bhuvan1G+1430 Dec 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Legal & Litigation

The promoter has declared 12 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
City Civil Court Goregaon Dindoshi3432015Hearing On Notice Of Motion
City Civil Court Goregaon Dindoshi3442015Hearing On Notice Of Motion
City Civil Court Goregaon Dindoshi3452015Hearing On Notice Of Motion
Small Cause Bandra1522010Evidence
Small Cause Bandra1532010Evidence
Small Cause Bandra1542010Evidence
Small Cause Bandra832010Evidence
Small Cause Bandra842010Evidence
Small Cause Bandra852010Evidence
Small Cause Bandra5392013Evidence
Small Cause Bandra5402013Evidence
Small Cause Bandra5412013Evidence

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.

FromExtended toStated reason
as registered30 Apr 2020Commencement Certificate recently received on 05/03/2019 and therefore it is not possible for us to complete the project on or before 31/12/2019. 100 % consent of the allottees is
30 Apr 202030 Apr 2020C.C is not granted by MCGM due to non compliance of some of the IOD conditions and that there are 3 Tenants who have field suit in the court in the year 2015. We have given underta
30 Apr 202031 Dec 2022Initially the proposed date of completion of the project was 31/12/2019. Subsequently an extension for 1 year under Section 6 of RERA was applied to which the RERA Authority grante

Location, Land & Connectivity

Located at Daulat Nagar, Road no. 7, Borivali, Mumbai Suburban, 400066. Per the filed land record, the plot is bounded to the north by By CTS No 2690 and 2691, to the south by By CTS No 2686, to the east by Daulat Nagar Road No 7 and to the west by By CTS No 2689. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~12 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Andheri MIDC / SEEPZ12 km
Powai / Hiranandani business park14 km
Chhatrapati Shivaji Int'l Airport16 km
Bandra Kurla Complex (BKC)19 km
Lower Parel / Worli business district27 km
Nariman Point / Fort35 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Borivali East

Proposed Redevelopment OF Prakashkunj Chsl
possession by Sep 2026 · Yash Realtors & Developers
Chandratej CHS LTD
possession by Oct 2026 · Elesh Ravjibhai Rathod
Eknath Gruh
possession by Oct 2026 · Vastav Developers PVT LTD
NEW Avanti Chsl
possession by Oct 2026 · Balaji Enterprises
Empire Vrindavan
possession by Nov 2026 · Empire Realty
66 Avenue
possession by Dec 2026 · Parsh Realtors

Major developers building in Borivali East

Other RERA-registered projects in Mumbai Suburban

Parmatma Villa
possession by Dec 2028 · Shrikant Satyanarayan Agarwal
Parque Residences
possession by Dec 2028 · M/s. New Grid Buildcon LLP
Parshuram Heights
possession by Sep 2028 · Spacewalk Realty LLP
Parshva Avenue
possession by Dec 2027 · Aarsh Construction
Parshwa Darshan CO Operative Housing Society Limited
possession by Dec 2027 · Svecha Realty LLP
Parshwa Darshan Phase 1
possession by Dec 2027 · Aarsh Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.