Mumbai/Project record

MahaRERA · the public record

PARSHWA HEIGHTS G WING

Palghar · PARASNATH BUILDERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000006004

Delivery and registration

When is the project declared for completion?

PARSHWA HEIGHTS G WING is registered with MahaRERA as P99000006004 and the promoter has declared completion for 31 Dec 2023.

31 Dec 2023

declared completion

33months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000006004
Registered on14 Aug 2017
Promoter-declared completion31 Dec 2023
Current statusCertificate Signed
Against todayabout 33 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for PARSHWA HEIGHTS G WING record 26 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 26 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Parasnath Builders is the promoter of record on 8 projects registered with MahaRERA, 3 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

8projects

registered with MahaRERA

3flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for PARSHWA HEIGHTS G WING in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+13.

BuildingWingsFloorsDeclared completion
PARSHWA HEIGHTS1G+1331 Mar 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered31 Mar 2021The project is on the verge of completion stage. The necessary documents have already been handed over to our authorised and approved architect for onward submission to the designa
31 Mar 202131 Dec 2023THE PROJECT IS COMPLETE IN ALL RESPECT BUT THE ENVIRONMENTAL AUTHORITY HAS SUSPENDED THE ISSUE OF ENVIRONMENTAL PERMISSION BUT OF RECENT THE ISSUE OF TEH SAME HAS STARTED AND WE AR

Location, Land & Connectivity

Located at Vasai, Palghar, 401303. Per the filed land record, the plot is bounded to the north by BUILDING NO 2, to the south by F WING, to the east by GARDEN and to the west by GARDEN. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~38 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ38 km
Powai / Hiranandani business park40 km
Chhatrapati Shivaji Int'l Airport42 km
Bandra Kurla Complex (BKC)45 km
Lower Parel / Worli business district52 km
Nariman Point / Fort60 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Parasnath Builders is the promoter on 2 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Parasnath Builders

Parasnath Builders
Past its declared completion datePalghar

Other RERA-registered projects in Virar West

Mayfair Virar Gardens Building NO 23, 24 And 25
possession by Sep 2026 · Mayfair Housing
Dattachhaya
possession by Nov 2026 · Jagdish Manohar Mhatre
Solaris Wing E-1 Hdil Layout
possession by Dec 2026 · Sunshine Developers
Star ERA
possession by Dec 2026 · Star Builders & Developers
Sugandhi Square
possession by Dec 2026 · R. N. Realty
Vitthal Haven
possession by Dec 2026 · Sushila Builders & Developers

Other RERA-registered projects in Palghar

Parshwanath Darshan
possession by Dec 2026 · Parshwanath Developers
Parshwanath Enclave
declared completion Sep 2020 · Chandrika Ashok Shah
Parth Devganga
possession by Dec 2027 · Parth Residency AND Infra LLP
Parth Plaza
possession by Dec 2027 · Zinal Builders AND Developers
Parvati Darshan Apartment
possession by Mar 2028 · Dhanlaxmi Construction
Parvati Garden
declared completion Dec 2021 · Swastik Enterprises

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026