Mumbai/Project record

MahaRERA · the public record

PIXEL

GHATKOPAR EAST · DHARMI PROPERTIES PVT LTD

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2028declared completionMahaRERA registration · read 12 Jul 2026
1registered unitsMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2028

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800048077

Delivery and registration

When is the project declared for completion?

PIXEL is registered with MahaRERA as P51800048077 and the promoter has declared completion for 31 Dec 2028.

31 Dec 2028

declared completion

27months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800048077
Registered on08 Dec 2022
Promoter-declared completion31 Dec 2028
Current statusCertificate Signed
Against today27 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for PIXEL record 18 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Dharmi Properties is the promoter of record on 7 projects registered with MahaRERA, 3 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

7projects

registered with MahaRERA

3flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

How much has actually been sold?

In PIXEL, 0 of 1 homes filed with MahaRERA are recorded as sold or booked, about 0%, and 1 remain available.

0%sold

0 of 1 homes

Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

The units recorded as unsold on the filing. The reckoner value is the government's ready-reckoner assessment the promoter filed against that unit, the figure stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home.

FloorUnitCarpetGovt reckoner value
Floor 16G+1610,624 sqft (987 sqm)₹18,000

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for PIXEL in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+19 and 1 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
PIXEL1G+19131 Dec 2028

Unit mix on the filing: 1 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Legal & Litigation

The promoter has declared 2 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
City Civil Court BombayS C SUIT NO 1755 OF 20212021Notice Of Motion Hearing
High Court Of Judicature At BombayL NO 8795 OF 20222022Intriem Application For Hearing

Location, Land & Connectivity

Located at GHATKOPAR EAST, 90 FEET ROAD, Kurla, Mumbai Suburban, 400077. Per the filed land record, the plot is bounded to the north by 90 FT WIDE ROAD, to the south by 30 FT WIDE EXISTING ROAD, to the east by CTS NO 195-85 and to the west by CTS NO 195-111. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~31 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Lower Parel / Worli business district31 km
Nariman Point / Fort32 km
Chhatrapati Shivaji Int'l Airport34 km
Bandra Kurla Complex (BKC)34 km
Andheri MIDC / SEEPZ36 km
Powai / Hiranandani business park39 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Ghatkopar East

Hema Apartments CO-Operative Housing Society Limited
possession by Sep 2026 · Hema Appartments CO-Operative Housing So
Centrona ZEN-A
possession by Dec 2026 · Elevated Avenue Realty LLP
Centrona ZEN-B
possession by Dec 2026 · Elevated Avenue Realty LLP
Centrona Zest- A
possession by Dec 2026 · Elevated Avenue Realty LLP
Centrona Zest- B
possession by Dec 2026 · Elevated Avenue Realty LLP
Ruparel Pristine
possession by Dec 2026 · Shiddhivinayak Developers

Major developers building in Ghatkopar East

Other RERA-registered projects in Mumbai Suburban

Pixel
possession by Dec 2028 · Apex Lifespaces
Planet Neptune
possession by Mar 2030 · AMI Housing Limited
Planning, Designing And Construction Of 196 MIG T/s And 2 Amenties At Mira Road
declared completion Dec 2019 · Maharashtra Housing AND Area Development
Platinum 53 West
possession by Dec 2028 · Platinumcorp Developers LLP
Platinum Avenue
possession by Dec 2026 · Platinumcorp Smart Realty LLP
Platinum Classic
possession by Jun 2029 · Platinumcorp Urban Developers LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026