Mumbai/Project record

MahaRERA · the public record

POONAM PARK

VEVOOR · POONAM LIFESTYLE

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000005516

Delivery and registration

When is the project declared for completion?

POONAM PARK is registered with MahaRERA as P99000005516 and the promoter has declared completion for 30 Dec 2023.

30 Dec 2023

declared completion

33months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000005516
Registered on11 Aug 2017
Promoter-declared completion30 Dec 2023
Current statusCertificate Signed
Against todayabout 33 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for POONAM PARK record 26 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 26 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Poonam Lifestyle is the promoter of record on 180 projects registered with MahaRERA, 43 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

180projects

registered with MahaRERA

43flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for POONAM PARK in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+10.

BuildingWingsFloorsDeclared completion
B NO 3 A WING1G+10-
B NO 3 B WING1G+10-
B NO 4 A WING1G+3-
B NO 4 B WING1G+10-
B NO 5 A WING1G+10-
B NO 5 B WING1G+10-
B NO 6 A WING1G+8-
B NO 6 B WING1G+8-
B NO 6 C WING1G+8-
B NO 6 D WING1G+8-
B NO 7 A WING1G+8-
B NO 7 B WING1G+8-
B NO 7 C WING1G+8-
B NO 7 D WING1G+8-
B NO 8 A WING1G+8-
B NO 9 A WING1G+8-
B NO 9 B WING1G+8-
B NO 9 C WING1G+8-
B NO 9 D WING1G+8-
B NO 10 A WING1G+8-
B NO 10 B WING1G+8-
B NO 10 C WING1G+8-
B NO 10 D WING1G+8-
B NO 11 A WING1G+8-
B NO 11 B WING1G+8-
B NO 11 C WING1G+8-
B NO 11 D WING1G+8-
B NO 11 E WING1G+8-
B NO 12 A WING1G+8-
B NO 12 B WING1G+8-
B NO 13 A WING1G+10-
B NO 14 A WING1G+8-
B NO 14 B WING1G+9-
B NO 15 A WING1G+8-
B NO 15 B WING1G+8-
B NO 15 C WING1G+8-
B NO 15 D WING1G+8-
B NO 16 A WING1G+8-
B NO 16 B WING1G+8-
B NO 16 C WING1G+8-
B NO 16 D WING1G+8-
B NO 16 E WING1G+8-
B NO 16 F WING1G+8-
B NO 17 A WING1G+8-
B NO 17 B WING1G+8-
B NO 17 C WING1G+8-
B NO 17 D WING1G+8-
B NO 18 A WING1G+8-
B NO 18 B WING1G+8-
B NO 2 A WING1G+8-
B NO 2 B WING1G+8-
B NO 1 A WING1G+2-

Legal and disputes

What disputes are disclosed?

15 complaints are on the MahaRERA record for POONAM PARK, with orders passed in 15 of them.

15complaints

15with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000016132426/10/2019VISHWANATH AMBAJI GHAG vs Poonam Lifestyleorder passed
CC00600000000175004/08/2018MAYANK KUMAR JAIN vs PARTNERS OF POONAM LIFESTYLEorder passed
CC00600000002281609/01/2018PRINCE JOHN vs M/S. POONAM LIFESTYLEorder passed
CC00600000002381721/03/2018Piyush Fatania vs Sumit Jain- Poonam Park (Poonam Developers)order passed
CC00600000008960605/08/2019SACHIN KHETAN vs POONAM LIFESTYLEorder passed
CC00600000004417719/04/2018Naresh Thakur vs Poonam Lifestyleorder passed
CC00600000005719011/12/2018Kaushal Ramniklal Pithadia vs Sumit Jawaharlal Jain / Ramesh Jugraj Mehtaorder passed
CC00600000005802309/02/2019Sunil Baraf vs Sumit Jawaharlal Jainorder passed
CC00600000007840309/03/2019Poonam Lifestyle vs Gurucharan Singh Anandorder passed
CC00600000007856919/03/2019Poonam Lifestyle vs Navprit Singh Anandorder passed
CC00600000007926112/05/2019SEMIL DAVE vs M/S. POONAM LIFESTYLEorder passed
CC00600000019871418/10/2021ASHISH SHARAD PATIL vs POONAM LIFESTYLEorder passed
CC00600000025148915/06/2022Ramdas Shankar Gaikwad vs Poonam Lifestyleorder passed
CC1250001101/01/2025Kishor Narsing Kamath vs POONAM LIFESTYLEorder passed
CC1260007005/01/2026RAJIV DILIPKUMAR PANDIT vs POONAM LIFESTYLEorder passed

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Add Session Court Palghar19/222022Discharge Application

Location, Land & Connectivity

Located at VEVOOR, ST. JOHN COLLEGE, Mumbai City, Mumbai City, 401404. Per the filed land record, the plot is bounded to the north by S NO 54 55, to the south by S NO 68, to the east by S NO 62 and to the west by S NO 60. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~64 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ64 km
Powai / Hiranandani business park66 km
Chhatrapati Shivaji Int'l Airport69 km
Bandra Kurla Complex (BKC)71 km
Lower Parel / Worli business district78 km
Nariman Point / Fort86 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Palghar

Parasnath Garden- SNO 200-1-2
possession by Sep 2026 · Shreenath Enterprises
SA Heights
possession by Sep 2026 · Atul Kumar Tripathi
SAI Park
possession by Sep 2026 · OM Siddhivinayak Developers
Shiv Krupa
possession by Oct 2026 · Shivaay Realty
V Square Arcade
possession by Oct 2026 · V Square
Nisarg Shrushti Phase-2
possession by Nov 2026 · Arvel Realtors

Major developers building in Palghar

Other RERA-registered projects in Palghar

Poonam Vista
declared completion Jun 2025 · Pabal Housing Private Limited
Poonam Vista Phase-II
declared completion May 2025 · Pabal Housing Private Limited
Prachiti Height
possession by May 2028 · Prachiti Entereprsies
Prajyot Apartment
possession by Jun 2027 · M/s. Pratiksha Associates
Prarthana CO-Operative Housing Society Limited
possession by Dec 2027 · Samartha Construction
Prashant Hill View
declared completion Sep 2019 · Shital Nitant Chavan

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026