MahaRERA Property Intelligence · Raigarh

PRAARAMBH SADANIKA

P52000053148 · KOLHARE NERAL · promoter Realtors

Certificate SignedDue 31 Dec 2026

Delivery & Registration

MahaRERA registrationP52000053148
Registered on17 Oct 2023
Promoter-declared completion31 Dec 2026
Current statusCertificate Signed
Against today5 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Construction Progress

MahaRERA's cost filing puts construction at ~81.8% of the estimated project cost incurred as of the last certificate (₹2.33 Cr spent against a ₹2.85 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Sales & Inventory

Of 28 homes filed with MahaRERA, 6 are sold/booked and 22 remain available (~21% sold) — early in sales — more choice of units now, but confirm the developer has the pre-sales to fund the build. Buyers have committed ₹88.72 Lakh in agreement value so far. Of that, ₹55.41 Lakh (~62%) is already collected, ₹33.31 Lakh receivable — a read on how far along these sales really are. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

What buyers actually paid: across 6 registered agreements, the effective carpet rate is ₹4,515/sqft (typical range ₹3,967–₹7,794) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.

The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:

FloorUnitCarpetReckoner value
Floor 1101319 sqft (29.67 sqm)₹12.67 Lakh
Floor 1103286 sqft (26.59 sqm)₹11.35 Lakh
Floor 1104292 sqft (27.15 sqm)₹11.59 Lakh
Floor 1105284 sqft (26.4 sqm)₹11.27 Lakh
Floor 1106276 sqft (25.67 sqm)₹10.96 Lakh
Floor 2201319 sqft (29.67 sqm)₹12.67 Lakh
Floor 2202276 sqft (25.67 sqm)₹10.96 Lakh
Floor 2203286 sqft (26.59 sqm)₹11.35 Lakh
Floor 2204292 sqft (27.15 sqm)₹11.59 Lakh
Floor 2206276 sqft (25.67 sqm)₹10.96 Lakh
Floor 3301319 sqft (29.67 sqm)₹12.67 Lakh
Floor 3302276 sqft (25.67 sqm)₹10.96 Lakh
Floor 3303286 sqft (26.59 sqm)₹11.35 Lakh
Floor 3304292 sqft (27.15 sqm)₹11.59 Lakh
Floor 3305284 sqft (26.4 sqm)₹11.27 Lakh
Floor 3306276 sqft (25.67 sqm)₹10.96 Lakh
Floor 4401319 sqft (29.67 sqm)₹12.67 Lakh
Floor 4402276 sqft (25.67 sqm)₹10.96 Lakh
Floor 4403286 sqft (26.59 sqm)₹11.35 Lakh
Floor 4404292 sqft (27.15 sqm)₹11.59 Lakh
Floor 4405284 sqft (26.4 sqm)₹11.27 Lakh
Floor 4406276 sqft (25.67 sqm)₹10.96 Lakh

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5 and 28 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
PRAARAMBH SADANIKA1G+528-

Unit mix on the filing: 28 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Dec 202531 Dec 2026Due to inadequate availability of funds the construction progress was slowed down and the project could not completed within the stipulated completion date 31.12.2025

Location, Land & Connectivity

Located at KOLHARE NERAL, KOLHARE, Ambarnath, Thane, 410101. Per the filed land record, the plot is bounded to the north by ADJN 9 M WIDE ROAD, to the south by ADJN LAYOUT BOUNDARY, to the east by ADJN PLOT NO 14 and to the west by ADJN LAYOUT BOUNDARY. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~46 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park46 km
Bandra Kurla Complex (BKC)49 km
Chhatrapati Shivaji Int'l Airport49 km
Andheri MIDC / SEEPZ50 km
Lower Parel / Worli business district53 km
Nariman Point / Fort54 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

See every S.b. Realtors project & its RERA track record →

Other RERA-registered projects in Neral

SAI Krupa Valley- Phase 1
possession by Aug 2026 · SAI Krupa Developers
Noble Apartment
possession by Aug 2026 · Asra Reality
Madina Complex
possession by Aug 2026 · Al-Hamd Developers
Arsh Apartment
possession by Sep 2026 · Mateen Rafique Patel
Naaz Plaza
possession by Sep 2026 · Prestige Reality
Aliza Apartments
possession by Dec 2026 · M/S SKY Homes

Major developers building in Neral

Other RERA-registered projects in Raigarh

Prabha
declared completion Dec 2018 · Shree Mahalaxmi Developers
Prabhat
declared completion Dec 2019 · Prabhat Creations LLP
Prabhavati Complex
declared completion Jul 2018 · Rahil Roshan Somjee
Prabhu Anant
declared completion Jun 2023 · Anant Builders & Developers
Prabhu DEV
declared completion Sep 2020 · Shree SAI Builders AND Developers
Prabhu LOK
declared completion Jun 2021 · Prabhu LOK Enterprises

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026