PRATHAMESH PLAZA

DOMBIVALLI EAST · MS. TIRUPATICONSTRUCTION

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

28 Feb 2021declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

28 Feb 2021

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700023026

Delivery and registration

When is the project declared for completion?

PRATHAMESH PLAZA is registered with MahaRERA as P51700023026 and the promoter has declared completion for 28 Feb 2021.

28 Feb 2021

declared completion

67months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700023026
Registered on14 Nov 2019
Promoter-declared completion28 Feb 2021
Current statusCertificate Signed
Against todayabout 67 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for PRATHAMESH PLAZA record 6 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 6 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for PRATHAMESH PLAZA in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+92.

BuildingWingsFloorsDeclared completion
PRATHAMESH PLAZA1G+9231 Aug 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at DOMBIVALLI EAST, KALYAN SHIL ROAD, Kalyan, Thane, 421203. Per the filed land record, the plot is bounded to the north by ROAD, to the south by ANIL PATIL BUILDING, to the east by GAONDEVI APARTMENT and to the west by VEGHNESH PLAZA. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Hedutane

Ambrin 3
possession by Sep 2026 · Impressions
Liana C
possession by Sep 2026 · Lodha Developers Limited
Casa Belvedere
possession by Oct 2026 · Lodha Developers Limited
Fiora G And H
possession by Oct 2026 · Lodha Developers Limited
Patels Pearl
possession by Oct 2026 · Pramukh Developers
Ashokas Empire
possession by Dec 2026 · Ashokas Empire

Major developers building in Hedutane

Other RERA-registered projects in Thane

Prathmesh
declared completion Dec 2022 · Axis Builders PVT LTD
Prathmesh Vrindavan F Wing
possession by Dec 2026 · S. P. Group
Pratik Greens-2
possession by Dec 2031 · Shirvawala Estate Developers LLP
Pravarsha Cooperative Housing Society Limited
declared completion Apr 2025 · Pravarsha CO-Operative Society Limited
Precious Avalon Phase-1
possession by Dec 2029 · Vinayak Associates
Precious Avenue
declared completion Dec 2025 · Metro Shivshakti Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026