MahaRERA Property Intelligence · Palghar

PRATHMESH DREAMS

P99000007940 · promoter Prathmesh Developers

Certificate SignedDue 30 Jun 2024

Delivery & Registration

MahaRERA registrationP99000007940
Registered on18 Aug 2017
Promoter-declared completion30 Jun 2024
Current statusCertificate Signed
Against todayabout 25 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Prathmesh Developers is the promoter of record on 13 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+13.

BuildingWingsFloorsDeclared completion
Prathmesh Dreams1G+13-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Jun 202430 Dec 2020OUR PROJECT DELAY REASON IS THAT WE HAVE SUBMITTED ALL REQUIRED PAPERS IN VASAI VIRAR MUNICIPAL CORPORATION FOR OCCUPATION CERTIFICATE BUT SINCE WE HAVE STILL NOT RECEIVED THE OCCU
30 Jun 202431 Dec 2023WE HAVE ALREADY APPLIED FOR THE OCCUPANCY CERTIFICATE TO VASAI VIRAR CITY MUNICIPAL CORPORATION ON 22/07/2019 BUT STILL IT IS NOT RECEIVED AND AWAITED DUE TO THE COVID PANADEMIC

Location, Land & Connectivity

Located at Borivali, Mumbai Suburban, 401303. Per the filed land record, the plot is bounded to the north by Garden, to the south by Internal Road, to the east by Wing J and to the west by Wing H. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~34 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ34 km
Powai / Hiranandani business park35 km
Chhatrapati Shivaji Int'l Airport39 km
Bandra Kurla Complex (BKC)41 km
Lower Parel / Worli business district49 km
Nariman Point / Fort58 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Prathmesh Developers is the promoter on 3 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Prathmesh Developers

Prathmesh Developers
FlaggedThane
Prathmesh Developers
FlaggedPalghar

Other RERA-registered projects in Virar West

Padman Residency
Not filing quarterly progress reports · possession by Jul 2026 · Hemant Parshuram Bhoir
Vinay Unique Residency Bldg NO 7
possession by Sep 2026 · Jasamrit Estates Private Limited
Mayfair Virar Gardens Building NO 23, 24 And 25
possession by Sep 2026 · Mayfair Housing
Dattachhaya
possession by Nov 2026 · Jagdish Manohar Mhatre
Solaris Wing E-1 Hdil Layout
possession by Dec 2026 · Sunshine Developers
Star ERA
possession by Dec 2026 · Star Builders & Developers

Major developers building in Virar West

Other RERA-registered projects in Palghar

Prathmesh Heights
declared completion Jun 2024 · Prathmesh Developers
Precilla CHS LTD
possession by Dec 2026 · Blue OAK Infrastructure
Prem Darshan
declared completion Mar 2023 · MK Builder & Developer
Premier Elegance
possession by Mar 2027 · Premear Landmark Developers LLP
Prestige Apartment
declared completion Dec 2021 · Saijayshreebuilders
Pride Apartment
declared completion Nov 2023 · Fine Homes

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026