MahaRERA Property Intelligence · Raigarh

PRIME

P52000003474 · DRONAGIRI · promoter Ess Gee Tradefin

Certificate SignedDue 31 Dec 2018

Delivery & Registration

MahaRERA registrationP52000003474
Registered on05 Aug 2017
Promoter-declared completion31 Dec 2018
Current statusCertificate Signed
Against todayabout 91 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Ess Gee Tradefin is the promoter of record on 7 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
PRIME1G+731 Dec 2018

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at DRONAGIRI, SECTOR 52, Thane, Thane, 400702. Per the filed land record, the plot is bounded to the north by PLOT NO 87, to the south by PLOT NO 85, to the east by PLOT NO 97 AND 98 AND 99 and to the west by 22 METERS WIDE ROAD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~19 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Nariman Point / Fort15 km
Lower Parel / Worli business district19 km
Bandra Kurla Complex (BKC)22 km
Chhatrapati Shivaji Int'l Airport25 km
Powai / Hiranandani business park27 km
Andheri MIDC / SEEPZ29 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

ESS GEE Tradefin PVT LTD is the promoter on 5 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by ESS GEE Tradefin PVT LTD

ESS GEE Tradefin PVT LTD
FlaggedRaigarh
ESS GEE Tradefin PVT LTD
FlaggedRaigarh
ESS GEE Tradefin PVT LTD
FlaggedRaigarh
ESS GEE Tradefin PVT LTD
FlaggedRaigarh

Other RERA-registered projects in Dronagiri

Astrova
possession by Jul 2026 · Kalpana Sterling Infra LLP
Jupiter Bliss
possession by Sep 2026 · Arjun Ashok Tarachandani
Shree Laxmi Coop Housing Society
possession by Sep 2026 · Mohit Mayuresh Gangal
Siddhivinayak Apartments
possession by Nov 2026 · Baldev Diwan Singh
Phoenix
possession by Dec 2026 · Adarsh Enterprises
Aaradhy Heights
possession by Dec 2026 · Lambodar Infra

Other RERA-registered projects in Raigarh

Prime Avenue
possession by Jun 2027 · Devraj Builders & Developers
Prime Corner
declared completion Feb 2021 · Prime Realties
Prime Diamond
declared completion Dec 2025 · Prime Abhishek Buildcon
Prime Exotica
declared completion Aug 2023 · Prime Homes
Prime Girija Homes
declared completion Apr 2024 · Devchand Baliram Koli
Prime Heritage
declared completion May 2023 · Hirji BAU Patel

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026