PRIMUS HOMES

KHARDI · K K NIRMAN & INFRASTRUCTURE LLP

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Oct 2028declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Oct 2028

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700035084

Delivery and registration

When is the project declared for completion?

PRIMUS HOMES is registered with MahaRERA as P51700035084 and the promoter has declared completion for 31 Oct 2028.

31 Oct 2028

declared completion

25months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700035084
Registered on10 May 2022
Promoter-declared completion31 Oct 2028
Current statusCertificate Signed
Against today25 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for PRIMUS HOMES record 20 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for PRIMUS HOMES in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
3A-3B1G+828 Feb 2026
Bungalow 11G+128 Feb 2027
Rowhouse 11G+128 Feb 2025
Rowhouse 21G+128 Feb 2025
Rowhouse 31G+128 Feb 2025
Rowhouse 41G+128 Feb 2025
Rowhouse 51G+128 Feb 2025
Rowhouse 61G+128 Feb 2022
Rowhouse 71G+128 Feb 2025
Rowhouse 81G+128 Feb 2025
Rowhouse 91G+128 Feb 2025
Rowhouse 101G+128 Feb 2025
Rowhouse 111G+128 Feb 2025
Rowhouse 121G+128 Feb 2025
Rowhouse 131G+128 Feb 2025
Rowhouse 141G+128 Feb 2025
Bungalow 21G+128 Feb 2027
Bungalow 31G+128 Feb 2027
1A1G+828 Feb 2027
1B1G+828 Feb 2027
2A1G+831 Oct 2028
2B1G+831 Oct 2028

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at KHARDI, THAPAR NAGAR, Kurla, Mumbai Suburban, 421601. Per the filed land record, the plot is bounded to the north by KHARDI RAILWAY LINE, to the south by BALANCE PLOT OF 187, to the east by 98 and to the west by NEAR LAND OF MURTUZA FAKIR. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~72 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park72 km
Andheri MIDC / SEEPZ74 km
Chhatrapati Shivaji Int'l Airport77 km
Bandra Kurla Complex (BKC)79 km
Lower Parel / Worli business district87 km
Nariman Point / Fort93 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Shahapur

Awasare Heights
possession by Sep 2026 · Rajkumar Tuljaram Aswani
Krishna Crown
possession by Oct 2026 · Shree Krishna Reality
Sava Arcade
possession by Oct 2026 · Sava Developers
Shantaram Park Residency
possession by Dec 2026 · Shubha Developers
Darshan Ganesh Apartment
possession by Dec 2026 · Tirupati Construction
Chintamani Meadows
possession by Dec 2026 · Jashnani Construction Private Limited

Major developers building in Shahapur

Other RERA-registered projects in Thane

Prince Avenue
declared completion Jun 2026 · Shakti Developers
Prince Galaxy
declared completion Jun 2024 · Ashtavinayak Construction Builders AND D
Prince Tower
possession by Dec 2029 · Prince India Developers
Prism Industrial Estate
declared completion Oct 2025 · Splendor Shelters PVT LTD
Pristine Tower
declared completion Mar 2021 · Ideal Developers
Pristine Views
declared completion Dec 2025 · Mindspace Developers

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026