MahaRERA Property Intelligence · Palghar

Prutha Residency

P99000014796 · Near JMT High School · promoter Aum Jivdani Associates

Certificate SignedDue 16 Dec 2021

Delivery & Registration

MahaRERA registrationP99000014796
Registered on02 Jan 2018
Promoter-declared completion16 Dec 2021
Current statusCertificate Signed
Against todayabout 55 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Aum Jivdani Associates is the promoter of record on 13 projects, of which 2 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+3.

BuildingWingsFloorsDeclared completion
Prutha Residency1G+316 Dec 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
16 Dec 202115 Dec 2022Continuous fears of lockdown affecting the work progress as well as the sales leading to delay
16 Dec 202115 Dec 2024due to covid ,non availabity of material and labour

Location, Land & Connectivity

Located at Near JMT High School, Vangaon Main Road, Dahanu, Palghar, 401103. Per the filed land record, the plot is bounded to the north by S No - 83A Pt, to the south by S No- 83A Pt, to the east by 30m Wide MDR ROad and to the west by S No - 83A pt. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~84 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ84 km
Powai / Hiranandani business park86 km
Chhatrapati Shivaji Int'l Airport88 km
Bandra Kurla Complex (BKC)91 km
Lower Parel / Worli business district98 km
Nariman Point / Fort106 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Vangaon

Ekta Parksville Phase II
possession by Dec 2026 · Ekta Parksville Homes Pvt. Ltd.
Galaxy Residency
Not filing quarterly progress reports · possession by Dec 2026 · Mahashakti Enterprises
Tanishq H AND I Wing
possession by Dec 2026 · Puneet Developers
Tanishq Type G-3,e-3,f-3 Wing J,k,l
possession by Dec 2026 · Rajvan Lifespaces LLP
Ivory Homes
possession by Jul 2027 · Yashron Developers LLP
Prime ONE
possession by Dec 2027 · Primeville Developers LLP

Other RERA-registered projects in Palghar

Puneet Developers - Tanishq F AND G Wing
declared completion Jul 2025 · Puneet Developers
Pushkarni Residency
declared completion Mar 2026 · M/S Shreeji & Associates
Pushp Vatika Phase 1
possession by Dec 2032 · BHU Satya Grihnirman LLP
Pushpam A
declared completion Jul 2018 · Arham Realtors
Pushpraj Industrial Park
possession by Mar 2027 · S K Developers
PVR Kingdom
possession by Jun 2028 · Pranit Vijay Raut

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026