MahaRERA Property Intelligence · Palghar

R K Apartment

P99000005413 · promoter Rk Enterprises

Certificate SignedDue 30 Sep 2019

Delivery & Registration

MahaRERA registrationP99000005413
Registered on11 Aug 2017
Promoter-declared completion30 Sep 2019
Current statusCertificate Signed
Against todayabout 82 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
R K Apartment1G+4-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Sep 201930 Sep 2019Revised Late due to Approval Pending from Town Planing now its Clear and We have Successfully Received our Revised Copy of Said Building/Project (RK APARTMENT).

Location, Land & Connectivity

Located at Vasai, Palghar, 401606. Per the filed land record, the plot is bounded to the north by S no 12-23, to the south by Building no 10, to the east by Building no 6 and to the west by Internal Road. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~110 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ110 km
Powai / Hiranandani business park111 km
Chhatrapati Shivaji Int'l Airport114 km
Bandra Kurla Complex (BKC)117 km
Lower Parel / Worli business district125 km
Nariman Point / Fort133 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

RK Enterprises is the promoter on 2 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by RK Enterprises

RK Enterprises
Past its declared completion datePalghar

Other RERA-registered projects in Talasari

Ajit Shanti Industrial Park
possession by Sep 2026 · Aamgaon 1 Infra Private Limited
Aradhya Heights
possession by Dec 2026 · Harshal Pandit Khairnar
Viroha City
possession by Dec 2026 · Prospective Estate And Realty Logical So
Shivalaya Complex
possession by Nov 2028 · Swastik Builders AND Developers
Dwarkaraj Towers
possession by Dec 2029 · Ronak Rajendra Mutha
Lotus Garden
possession by Dec 2029 · Omkar Infra

Other RERA-registered projects in Palghar

R K Apartment 2
declared completion Dec 2024 · RK Enterprises
R.k.complex
declared completion Dec 2022 · Shree Enterprises
Raajlaxmi Avenue
possession by Dec 2026 · Magnus Infracon
Raajlaxmi Towers
declared completion Dec 2025 · Rajlaxmi Developers
Rachna Towers
declared completion Dec 2019 · Vikram Buildwell PVT LTD
Radha Heights
possession by Dec 2027 · Radha Builders And Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026