Mumbai/Project record

MahaRERA · the public record

RAJLAXXMI PARK

SAPHALE · SAPHALE LAND DEVELOPERS LLP

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

211units filed as unsoldInventory · 19 September 2026
31 Dec 2030declared completionMahaRERA registration · read 12 Jul 2026
341registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2030

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000056103

Delivery and registration

When is the project declared for completion?

RAJLAXXMI PARK is registered with MahaRERA as P99000056103 and the promoter has declared completion for 31 Dec 2030.

31 Dec 2030

declared completion

51months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000056103
Registered on10 May 2024
Promoter-declared completion31 Dec 2030
Current statusCertificate Signed
Against today51 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for RAJLAXXMI PARK record 16 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 16 quarterly progress reports on record since registration, with no current default.

Construction

How much construction cost has been reported?

In RAJLAXXMI PARK, ₹5.76 Cr of a declared ₹47.68 Cr estimated project cost is reported as incurred, about 12.1%, as at the last certified filing with MahaRERA.

12.1%

₹5.76 Cr

of ₹47.68 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In RAJLAXXMI PARK, 44 of 255 homes filed with MahaRERA are recorded as sold or booked, about 17%, and 211 remain available.

17%sold

44 of 255 homes

₹10.38 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹6.42 Cr (about 62%) is recorded as collected and ₹3.96 Cr as receivable. The project registers 341 homes in total, while this sold/unsold inventory filing covers 255 of them.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 44 registered agreements, the effective carpet rate is ₹5,654/sqft, with eight in ten falling between ₹5,232 and ₹6,903 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

The inventory filing also declares: 81 owner/investor-held and 5 not for sale.

What the filings record, home by home

Read from MahaRERA on 19 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 44 homes carry one, and 211 of the 341 are recorded unsold.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
102495 sqftRs 27.07 lakh typical, over Rs 16.00 lakh to Rs 27.95 lakh20 filed at this size

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.

In RAJLAXXMI PARK, 144 of the 211 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 210 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7 and 341 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
BLDG NO 1 WING A AND B1G+78731 Dec 2030
BLDG NO 21G+43231 Dec 2030
BLDG NO 3 WING A AND B1G+45931 Dec 2030
BLDG NO 4 WING A AND B1G+79131 Dec 2030
BLDG NO 51G+44331 Dec 2030
HOUSING FOR THE AFFECTED PEOPLE1G+42931 Dec 2030

Unit mix on the filing: 314 residential and 27 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at SAPHALE, RAMBAG, Palghar, Palghar, 401102. Per the filed land record, the plot is bounded to the north by GAT NO 84 HISSA NO B LAND AND ROAD, to the south by GAT NO 84 A, to the east by BY GAT NO 84 A and to the west by INTERNAL ROAD TOWARDS SHILTE PADA. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~49 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ49 km
Powai / Hiranandani business park51 km
Chhatrapati Shivaji Int'l Airport53 km
Bandra Kurla Complex (BKC)56 km
Lower Parel / Worli business district63 km
Nariman Point / Fort71 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Makane

Excellence Residency 3
possession by Dec 2026 · SAI Excellence Developers
Nayan-Vastu Heritage
Not filing quarterly progress reports · possession by Dec 2026 · Unity Infra
Nayan-Vastu Heritage
possession by Dec 2026 · Unity Infra
Nine Star Prestige Building NO. 1
possession by Dec 2026 · Nine Home Creators
Nine Star Prestige Building NO. 2
possession by Dec 2026 · Nine Home Creators
Ninestar Crown Bldg NO 5 Emerald
possession by Dec 2026 · Nine Homemakers

Other RERA-registered projects in Palghar

Rajmandir Gardens
possession by Dec 2027 · Raj Mandir Reality
Rajshree Complex
possession by Jun 2031 · Nyra Builders LLP
Rajshree Complex Building NO 1 Wing B
possession by Dec 2030 · Nine Land Developers
Rajsuraksha Complex
possession by Sep 2027 · Rajsuraksha Infra Developers
Rajvir Estate No.2
possession by Jan 2029 · Rajvir Enterprise
Rajyog Gardens
possession by Dec 2027 · Rajyog Infra

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026