RAKHI TOWER PHASE 3 12TH TO 15TH FLOOR PART

BORIVALI · WESTERN DEVELOPMENTS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jun 2026declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800027354

Delivery and registration

When is the project declared for completion?

RAKHI TOWER PHASE 3 12TH TO 15TH FLOOR PART is registered with MahaRERA as P51800027354 and the promoter has declared completion for 30 Jun 2026.

30 Jun 2026

declared completion

3months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800027354
Registered on06 Dec 2020
Promoter-declared completion30 Jun 2026
Current statusCertificate Signed
Against todayabout 3 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for RAKHI TOWER PHASE 3 12TH TO 15TH FLOOR PART record 23 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Western Developments is the promoter of record on 10 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

10projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for RAKHI TOWER PHASE 3 12TH TO 15TH FLOOR PART in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+3.

BuildingWingsFloorsDeclared completion
RAKHI TOWER PHASE 3 12TH TO 15TH FLOOR PART1G+331 Dec 2025

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Legal & Litigation

The promoter has declared 5 court cases on this project to MahaRERA. 3 are still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Bombay High CourtWP/319/2014, WPL/2333/20132013Admitted
Bombay High CourtWP/2850/2014,WPL/2797/2014,NMW839/20162014Pending Instructions
Bombay High CourtAPL/1091/2014,APL/521/20152015Listed
Bombay High Court580 OF 2019 NOTICE OF MOTION NO 2302 0F 20192019Pending
Bombay High Court1027 OF 2019 NOTICE OF MOTION NO 2302 OF 20192019Pending

Location, Land & Connectivity

Located at BORIVALI, RAKHI TOWER, CTS NO 332, 332C, NEAR LAKSH LABH BUILDING, KANHERI VILLAGE, KASTURBA ROAD NO 3, BORIVALI EAST, MUMBAI-400066 , Borivali, Mumbai Suburban, 400066. Per the filed land record, the plot is bounded to the north by PLOT BEARING CTS NO 342, to the south by LAKSHA LABH SOCIETY, to the east by KASTURBA CROSS ROAD NO 3 and to the west by PLOT BEARING CTS NO 334 AND 341. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Western Developments is the promoter on 3 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Western Developments

Western Developments
Not filing quarterly progress reportsMumbai Suburban

Other RERA-registered projects in Borivali East

Proposed Redevelopment OF Prakashkunj Chsl
possession by Sep 2026 · Yash Realtors & Developers
Chandratej CHS LTD
possession by Oct 2026 · Elesh Ravjibhai Rathod
Eknath Gruh
possession by Oct 2026 · Vastav Developers PVT LTD
NEW Avanti Chsl
possession by Oct 2026 · Balaji Enterprises
Empire Vrindavan
possession by Nov 2026 · Empire Realty
66 Avenue
possession by Dec 2026 · Parsh Realtors

Major developers building in Borivali East

Other RERA-registered projects in Mumbai Suburban

Rakshi-Elanza
possession by Mar 2027 · OM SAI Builders & Developers
Rakyan Imperia
possession by Sep 2027 · RR Brickcon LLP
RAM Chhaya
possession by Dec 2026 · Prime Infra
RAM Dutt CO-Operative Housing Society LTD
declared completion Jun 2023 · Samarpan Homes & Developers
RAM Rameshwar Darshan Chsl
declared completion Jun 2024 · Ferro Build
Ramaakrishna
possession by Apr 2027 · Nine Dimensions Housing LLP

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.