REGENCY PRIME

KURLA CAMP · DHAANIYA ENTERPRISES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

43units filed as unsoldInventory · 12 September 2026
31 Dec 2027declared completionMahaRERA registration · read 12 Jul 2026
48registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2027

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700051258

Delivery and registration

When is the project declared for completion?

REGENCY PRIME is registered with MahaRERA as P51700051258 and the promoter has declared completion for 31 Dec 2027.

31 Dec 2027

declared completion

15months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700051258
Registered on08 Jun 2023
Promoter-declared completion31 Dec 2027
Current statusCertificate Signed
Against today15 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for REGENCY PRIME record 14 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Dhaaniya Enterprises is the promoter of record on 2 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

2projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

How much has actually been sold?

In REGENCY PRIME, 5 of 48 homes filed with MahaRERA are recorded as sold or booked, about 10%, and 43 remain available.

10%sold

5 of 48 homes

₹1.23 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹68.58 Lakh (about 56%) is recorded as collected and ₹53.92 Lakh as receivable.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 5 registered agreements, the effective carpet rate is ₹4,557/sqft, with eight in ten falling between ₹4,478 and ₹4,557 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

What the filings record, home by home

Read from MahaRERA on 12 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 5 homes carry one, and 43 of the 48 are recorded unsold.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
102604 sqftRs 27.50 lakh3 filed on this stack, floors 5–10

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.

In REGENCY PRIME, every one of the 43 unsold homes has agreements filed on its own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 42 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+12 and 48 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
REGENCY PRIME1G+124831 Dec 2027

Unit mix on the filing: 48 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at KURLA CAMP, NEAR KALI MATA MANDIR, Ulhasnagar, Thane, 421004. Per the filed land record, the plot is bounded to the north by 18M WIDE DP ROAD, to the south by ADJECENT PROPERTY AND CTS NO 22825 P 22827 P, to the east by CTS NO 22818 P and to the west by ADJECENT PROPERTY. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~30 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park30 km
Andheri MIDC / SEEPZ33 km
Chhatrapati Shivaji Int'l Airport35 km
Bandra Kurla Complex (BKC)35 km
Lower Parel / Worli business district43 km
Nariman Point / Fort48 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Dhaaniya Enterprises is the promoter on 2 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other RERA-registered projects in Ulhasnagar

Ganga Residency
possession by Sep 2026 · MR Ravi Yallappa Vhatkar
Jhalak Arena
possession by Dec 2026 · Jhalak Constructions
Roshan Galaxy
possession by Dec 2026 · Royal Group
SEA Green Aurus
possession by Feb 2027 · Sea Green Homes
Elite Crystal
possession by Jun 2027 · Elite Ulhas
Fortune Galaxy
possession by Jul 2027 · Sai Construction

Other RERA-registered projects in Thane

Regency Sapphire
declared completion Jun 2026 · Regency Nirman LTD
Regency Sarvam Phase - 10
declared completion Dec 2019 · Regency Nirman LTD
Regency Sarvam Phase 13
declared completion Dec 2025 · Regency Nirman LTD
Regency Solitaire
possession by Dec 2032 · Johar Hasan Zojwalla
Regency Square
possession by Dec 2030 · Regency Infrabuild LLP
Regency Vertex
possession by Dec 2028 · Regency Buildspaces LLP

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.