RELAX COUNTY - B - PHASE 2

Thane · RAJENDRA YASHWANT PATIL

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Mar 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Mar 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700014335

Delivery and registration

When is the project declared for completion?

RELAX COUNTY - B - PHASE 2 is registered with MahaRERA as P51700014335 and the promoter has declared completion for 30 Mar 2022.

30 Mar 2022

declared completion

54months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700014335
Registered on23 Nov 2017
Promoter-declared completion30 Mar 2022
Current statusCertificate Signed
Against todayabout 54 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for RELAX COUNTY - B - PHASE 2 record 18 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 18 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Rajendra Yashwant Patil is the promoter of record on 172 projects registered with MahaRERA, 25 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

172projects

registered with MahaRERA

25flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

How much has actually been sold?

In RELAX COUNTY - B - PHASE 2, 4 of 77 plots filed with MahaRERA are recorded as sold or booked, about 5%, and 73 remain available.

5%sold

4 of 77 plots

Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for RELAX COUNTY - B - PHASE 2 in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Kalyan, Thane, 421602. Per the filed land record, the plot is bounded to the north by OPEN SPACE OF RELAX COUNTY B PHASE 3, to the south by RELAX COUNTY A, to the east by RELAX COUNTY B PHASE 1 and to the west by AMENITY 1 SPACE OF RELAX COUNTY PHASE 4. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~87 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park87 km
Andheri MIDC / SEEPZ89 km
Chhatrapati Shivaji Int'l Airport92 km
Bandra Kurla Complex (BKC)94 km
Lower Parel / Worli business district102 km
Nariman Point / Fort109 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Thane

Elegant City Bliss
possession by Jun 2028 · Neele Buildcon LLP
THE White Villas Kasara Phase 2
possession by Dec 2029 · St. Angelo's Vnct Ventures Pvt. Ltd.
THE White Villas Kasara
declared completion Dec 2025 · St. Angelo's Vnct Ventures Pvt. Ltd.

Other RERA-registered projects in Thane

Reliance Gold
possession by Feb 2028 · Golden Enterprises
Renaissance Industrial Smart City - PH I
possession by Dec 2031 · Renaissance Indus Infra Private Limited
Renaissance Industrial Smart City - PH II
possession by Dec 2038 · Renaissance Indus Infra Private Limited
Renuka CHS
possession by Dec 2026 · Neelpadma Constructions
Residential Buildings Of LIG MIG HIG At Balkum Thane Under Lum Sum Turnkey
declared completion Feb 2024 · Konkan Housing AND Area Development Boar
Rex Residency
possession by Dec 2028 · Ekdanta Developers Private Limited

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.