Mumbai/Project record

MahaRERA · the public record

RIJIN PRIDE

Daulat Nagar, BORIVALI EAST · SURBHI CONSTRUCTION

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

13units filed as unsoldInventory · 20 September 2026
30 Sep 2028declared completionMahaRERA registration · read 12 Jul 2026
32registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Sep 2028

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · PM1180002501482

Delivery and registration

When is the project declared for completion?

RIJIN PRIDE is registered with MahaRERA as PM1180002501482 and the promoter has declared completion for 30 Sep 2028.

30 Sep 2028

declared completion

24months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationPM1180002501482
Registered on17 Nov 2025
Promoter-declared completion30 Sep 2028
Current statusCertificate Signed
Against today24 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for RIJIN PRIDE record 2 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 2 quarterly progress reports on record since registration, with no current default.

Construction

How much construction cost has been reported?

In RIJIN PRIDE, ₹0 of a declared ₹4.75 Cr estimated project cost is reported as incurred, about 0.0%, as at the last certified filing with MahaRERA.

0.0%

₹0

of ₹4.75 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In RIJIN PRIDE, 0 of 13 homes filed with MahaRERA are recorded as sold or booked, about 0%, and 13 remain available.

0%sold

0 of 13 homes

Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. The project registers 32 homes in total, while this sold/unsold inventory filing covers 13 of them.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

The units recorded as unsold on the filing. The reckoner value is the government's ready-reckoner assessment the promoter filed against that unit, the figure stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home.

FloorUnitCarpetGovt reckoner value
Floor 1SHOP NO 7565 sqft (52.52 sqm)₹91.49 Lakh
Floor 101001700 sqft (65.01 sqm)₹83.03 Lakh
Floor 101002700 sqft (65.01 sqm)₹83.03 Lakh
Floor 111101700 sqft (65.01 sqm)₹83.03 Lakh
Floor 111102700 sqft (65.01 sqm)₹83.03 Lakh
Floor 121201700 sqft (65.01 sqm)₹83.03 Lakh
Floor 121202700 sqft (65.01 sqm)₹83.03 Lakh
Floor 131301700 sqft (65.01 sqm)₹83.03 Lakh
Floor 131302700 sqft (65.01 sqm)₹83.03 Lakh
Floor 141401700 sqft (65.01 sqm)₹83.03 Lakh
Floor 141402700 sqft (65.01 sqm)₹83.03 Lakh
Floor 6602735 sqft (68.31 sqm)₹87.25 Lakh
Ground/Floor 0SHOP NO 41,229 sqft (114.18 sqm)₹1.99 Cr

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for RIJIN PRIDE in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 20 September 2026

What the filings record, home by home

Read from MahaRERA on 20 September 2026

No home in RIJIN PRIDE carries a registered agreement value on its MahaRERA filing, so there is no record here of what anyone has paid. What the promoter has filed is the government ready reckoner value for 13 homes — the Annual Statement of Rates valuation, with each home’s carpet area and floor already applied. Across them that is Rs 11,866 a sq ft typical, over Rs 11,866 to Rs 16,184.

A reckoner value is the basis stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home to you.

The Reckoner Record lists all 13 of them — each home, its RERA carpet area, the valuation filed against it and the rate that works out to. It is the filing copied, not a reading of it.

See all 13 filed valuations — ₹999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+16 and 32 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
RIJIN PRIDE1G+1632-

Unit mix on the filing: 25 residential and 7 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Daulat Nagar, BORIVALI EAST, Daulat Nagar Road No.3, Borivali, Mumbai Suburban, 400066. Per the filed land record, the plot is bounded to the north by Yogeeta Co-operative Housing Society Ltd., to the south by Choudhary Co-operative Housing Society Ltd, to the east by Daulat nagar, Road No-03. and to the west by Swami Vivekanand Road.. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~12 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Andheri MIDC / SEEPZ12 km
Powai / Hiranandani business park14 km
Chhatrapati Shivaji Int'l Airport17 km
Bandra Kurla Complex (BKC)19 km
Lower Parel / Worli business district27 km
Nariman Point / Fort35 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Not Available is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Not Available

Not Available
FlaggedMumbai Suburban

Other RERA-registered projects in Borivali East

Proposed Redevelopment OF Prakashkunj Chsl
possession by Sep 2026 · Yash Realtors & Developers
Chandratej CHS LTD
possession by Oct 2026 · Elesh Ravjibhai Rathod
Eknath Gruh
possession by Oct 2026 · Vastav Developers PVT LTD
NEW Avanti Chsl
possession by Oct 2026 · Balaji Enterprises
Empire Vrindavan
possession by Nov 2026 · Empire Realty
66 Avenue
possession by Dec 2026 · Parsh Realtors

Major developers building in Borivali East

Other RERA-registered projects in Mumbai Suburban

Rijin Twinstar
possession by Nov 2029 · Not Available
Rishab Aangan
possession by Jun 2028 · Rishab Infra
Rishab Laxmi
possession by Dec 2026 · Aditi Developers
Rishab LUV Kush Chsl LTD
possession by Jun 2028 · Rishab Infra
Rishab Mahesh Darshan
possession by Jun 2029 · Rishab Infra
Rishab OM Brij Kutir
possession by Dec 2027 · Rishab Infra

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026