Mumbai/Project record

MahaRERA · the public record

RITIKA HEIGHTS

TEMBHODE VILLAGE · AKAJIT DEVELOPERS LLP

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2026declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000055116

Delivery and registration

When is the project declared for completion?

RITIKA HEIGHTS is registered with MahaRERA as P99000055116 and the promoter has declared completion for 31 Dec 2026.

31 Dec 2026

declared completion

3months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000055116
Registered on04 Mar 2024
Promoter-declared completion31 Dec 2026
Current statusCertificate Signed
Against today3 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for RITIKA HEIGHTS record 10 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for RITIKA HEIGHTS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
RITIKA HEIGHTS - BUILDING NO 41G+631 Dec 2026

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for RITIKA HEIGHTS, with orders passed in 0 of them.

1complaint

0with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC1260429909/07/2026lata ramesh salot vs AKAJIT DEVELOPERS LLPpending / no order on file

Location, Land & Connectivity

Located at TEMBHODE VILLAGE, TEMBHODE ROAD, Borivali, Mumbai Suburban, 401404. Per the filed land record, the plot is bounded to the north by ROAD, to the south by ROAD, to the east by ROAD and to the west by PROPERTIES OF MR KUDU. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Palghar

Parasnath Garden- SNO 200-1-2
possession by Sep 2026 · Shreenath Enterprises
SA Heights
possession by Sep 2026 · Atul Kumar Tripathi
SAI Park
possession by Sep 2026 · OM Siddhivinayak Developers
Shiv Krupa
possession by Oct 2026 · Shivaay Realty
V Square Arcade
possession by Oct 2026 · V Square
Nisarg Shrushti Phase-2
possession by Nov 2026 · Arvel Realtors

Major developers building in Palghar

Other RERA-registered projects in Palghar

Ritu Gardenia Phase 2
possession by Dec 2027 · Ritu Builders AND Developers
Riyansh Enclave
possession by Dec 2027 · Vardaan Realtors
RK Complex 1
possession by Dec 2027 · Shree Enterprises
Rohini Heights Building No 3 Wing - A Type - 5
possession by Dec 2026 · Lalitkumar Poonamsingh Rajpurohit
Roman Residency
declared completion Feb 2021 · Shantee Housing
Roman Residency
declared completion Dec 2023 · Shantee Housing

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026