MahaRERA Property Intelligence · Thane

Riverview Classic Building No 4, Phase IV

P51700017199 · Kalyan West · promoter Rutu Builders

Certificate SignedDue 30 Dec 2022

Delivery & Registration

MahaRERA registrationP51700017199
Registered on23 Jul 2018
Promoter-declared completion30 Dec 2022
Current statusCertificate Signed
Against todayabout 43 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Rutu Builders is the promoter of record on 24 projects, of which 2 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+16.

BuildingWingsFloorsDeclared completion
Building No 41G+16-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Court Of Additional District And Sessions Court Kalyan70 of 20142014Matter Is For Hearing For Application

Location, Land & Connectivity

Located at Kalyan West, Adharwadi Road, Thane, Thane, 421301. Per the filed land record, the plot is bounded to the north by 45 M Wide DP road, to the south by S No 25 P, to the east by S no 11 P and to the west by S No 25 P. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Rutu Builders is the promoter on 3 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Rutu Builders

Other RERA-registered projects in Kalyan

Tharwani Solitaire Phase IV
possession by Jul 2026 · Anil Hardasmal Tharwani
Kailash Gardens
possession by Jul 2026 · Shree Laxmi Enterprises
Mangeshi Ambar
possession by Jul 2026 · Mangesh Dashrath Gaikar
Mangeshi Tulip
possession by Jul 2026 · Mangesh Dashrath Gaikar
Anand 21 Uptown
possession by Aug 2026 · VPA Developers
Pawan Atharva Phase I
possession by Aug 2026 · Pawan Real Estate

Major developers building in Kalyan

Other RERA-registered projects in Thane

Riverwood Park Building No -1
possession by Mar 2027 · Shree Khidkaleshwar Property Developers
Riverwood Park Building No. 2
declared completion Sep 2023 · Shree Khidkaleshwar Property Developers
Riverwood Park Building No -3
possession by Jun 2027 · Shree Khidkaleshwar Property Developers
Riverwood Park Building No. 4
declared completion Oct 2023 · Shree Khidkaleshwar Property Developers
Riverwood Park Building No. 5
declared completion Feb 2025 · Shree Khidkaleshwar Property Developers
Riviera - Building No.1
declared completion Sep 2024 · Shreeram Builders

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026