Mumbai/Project record

MahaRERA · the public record

ROYAL HILLS

Mumbai City · GREEN SKY DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2019declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2019

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000012710

Delivery and registration

When is the project declared for completion?

ROYAL HILLS is registered with MahaRERA as P52000012710 and the promoter has declared completion for 31 Dec 2019.

31 Dec 2019

declared completion

81months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000012710
Registered on07 Sep 2017
Promoter-declared completion31 Dec 2019
Current statusCertificate Signed
Against todayabout 81 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for ROYAL HILLS record 10 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 10 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Green Sky Developers is the promoter of record on 197 projects registered with MahaRERA, 25 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

197projects

registered with MahaRERA

25flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for ROYAL HILLS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+3.

BuildingWingsFloorsDeclared completion
BUILDING A1G+331 Dec 2018
BUILDING B1G+331 Dec 2018
BUILDING C1G+331 Dec 2018
BUILDING D1G+331 Dec 2018
BUILDING E1G+331 Dec 2018

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2019Due to heavy rain fall in the month of june, july, and august in 2018 and non availability of construction material . Specially sand the project is delayed. We request you to pr

Location, Land & Connectivity

Located at Mumbai City, Mumbai City, 410201. Per the filed land record, the plot is bounded to the north by SURVEY NO 43, to the south by HISSA NO 7 AND 2, to the east by ROAD COMING FROM DAHIVALI and to the west by SURVEY NO 73. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~51 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park51 km
Bandra Kurla Complex (BKC)53 km
Chhatrapati Shivaji Int'l Airport54 km
Lower Parel / Worli business district55 km
Nariman Point / Fort55 km
Andheri MIDC / SEEPZ55 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Karjat

Dhanlaxmi Heights
possession by Sep 2026 · Dhanlaxmi Developers
Warai Woods Ph 2
Not filing quarterly progress reports · possession by Nov 2026 · Nahar Riddhi Siddhi Developers
Jambrung Valley
possession by Nov 2026 · Kirtiraj Nanasaheb Sawant
Bliss Studio
possession by Dec 2026 · Balsam Builders
Beverly Hills
possession by Dec 2026 · Rudram Infra Projects Private Limited
Jupiter Heights
Not filing quarterly progress reports · possession by Dec 2026 · Jupiter Heights

Major developers building in Karjat

Other RERA-registered projects in Raigarh

Royal Palace
declared completion Apr 2020 · Abdul Sattar Rahimuddin Khan
Royal Palm
possession by Dec 2026 · Marquis Builders
Royal Paradise
declared completion Nov 2022 · Zishan Builders AND Developers
Royal Paradise
possession by Oct 2029 · Azpiria Builders & Developers LLP
Royal Plaza
declared completion Dec 2018 · Royal Enterprise
Royal Plaza
declared completion Jun 2026 · Royal Group

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026