Mumbai/Project record

MahaRERA · the public record

ROYAL PRISTO

VAISHETPADA KURAR VILLAGE MALAD EAST · ROYAL REALTORS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2026declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800019529

Delivery and registration

When is the project declared for completion?

ROYAL PRISTO is registered with MahaRERA as P51800019529 and the promoter has declared completion for 30 Dec 2026.

30 Dec 2026

declared completion

3months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800019529
Registered on08 Feb 2019
Promoter-declared completion30 Dec 2026
Current statusCertificate Signed
Against today3 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for ROYAL PRISTO record 30 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Royal Realtors is the promoter of record on 182 projects registered with MahaRERA, 27 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

182projects

registered with MahaRERA

27flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for ROYAL PRISTO in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+35.

BuildingWingsFloorsDeclared completion
ROYAL PRISTO1G+35-
ROYAL PARV1G+27-

Legal and disputes

What disputes are disclosed?

4 complaints are on the MahaRERA record for ROYAL PRISTO, with orders passed in 2 of them.

4complaints

2with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000030299911/10/2022Mahesh Eknath Patole vs Royal Realtorsorder passed
CC1250045811/02/2025ROYAL REALTORS vs mehbubbi Mohdhani khanorder passed
CC1260342704/06/2026Kekin Prakash Patel vs ROYAL REALTORSpending / no order on file
CC1260313926/05/2026SUSHANT SURESH AMBEKAR vs ROYAL REALTORSpending / no order on file

Legal & Litigation

The promoter has declared 3 court cases on this project to MahaRERA. 1 is still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
City Civil Court Dindoshi11532017Pending
Bombay High Court14602019The Writ Petition Is Dismissed
Bombay High Court11712019The Writ Petition Is Dismissed

Location, Land & Connectivity

Located at VAISHETPADA KURAR VILLAGE MALAD EAST, SANTOSHI MATA TEMPLE ROAD, Borivali, Mumbai Suburban, 400097. Per the filed land record, the plot is bounded to the north by 13 4 MT WIDE PROPOSED DP ROAD, to the south by EXISTING BLDG, to the east by EXISTING BLDG and to the west by 18 3 MT WIDE DP ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~6 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Andheri MIDC / SEEPZ6 km
Powai / Hiranandani business park9 km
Chhatrapati Shivaji Int'l Airport11 km
Bandra Kurla Complex (BKC)13 km
Lower Parel / Worli business district21 km
Nariman Point / Fort29 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Royal Realtors is the promoter on 4 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Royal Realtors

Royal Realtors
Past its declared completion dateMumbai Suburban

Other RERA-registered projects in Malad East

Amann Highland Park
possession by Oct 2026 · MS Relliance Construction CO
Gami And Jaydeep Ventura Commercial Hub
possession by Oct 2026 · M/S Real Infrastructure CO
Parmar Pearl - JAY Koteshwar Nagar CHS LTD
possession by Nov 2026 · Parmar Constructions Private Limited
Neelyog Virat -A Wing
possession by Dec 2026 · Neelyog Construction Pvt Ltd
Spring Meadows
possession by Dec 2026 · Renaissance Enterprises
Anant Nakshatra Tower 1
possession by Dec 2026 · M Construction Company

Other RERA-registered projects in Mumbai Suburban

Royal Regency Heights
possession by Dec 2028 · Mahesh Amrutlal Boriya
Royal Stone
declared completion Nov 2024 · Vaibhavlaxmi Builders & Developers
Royale
possession by Sep 2026 · Khoker Synergy Developers
Royale 22
declared completion May 2026 · VS Developers
Royale Rose
possession by Dec 2028 · Project One
Royce Residences
possession by Jun 2030 · Maxrich Infra Private Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026