RTG Shiv Srishti

kalyan · RTG Infrastructure and Realtors Limited

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2028declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2028

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700012322

Delivery and registration

When is the project declared for completion?

RTG Shiv Srishti is registered with MahaRERA as P51700012322 and the promoter has declared completion for 30 Dec 2028.

30 Dec 2028

declared completion

27months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700012322
Registered on01 Sep 2017
Promoter-declared completion30 Dec 2028
Current statusCertificate Signed
Against today27 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for RTG Shiv Srishti record 39 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Rtg Infrastructure is the promoter of record on 2 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

2projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for RTG Shiv Srishti in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+24.

BuildingWingsFloorsDeclared completion
Type A1G+24-
Type D1G+11-

Legal and disputes

What disputes are disclosed?

6 complaints are on the MahaRERA record for RTG Shiv Srishti, with orders passed in 5 of them.

6complaints

5with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000000141726/11/2017Reena Abhay Bhanushali and others vs Prakash Gadiaorder passed
CC00600000000154929/10/2017Sagar Dighe vs PRAKASH HEMRAJ GADIYAorder passed
CC00600000002321707/02/2018Santosh T. Sathe vs Prakash H. Gadiyaorder passed
CC00600000002339517/02/2018Nitin D. Khachane vs Prakash Gadiyaorder passed
CC00600000010033917/08/2019VINOD RATILAL THAKKAR vs RTG INFRASTRUCTURE AND REALTORS LTDorder passed
CC00600000029227707/08/2022RTG SHIV SRISHTI ASSOCIATION OF ALLOTTES ASSOCIATION OF ALLOTTEES vs RTG INFRASTUCTURE & REALTORS LTDpending / no order on file

Legal & Litigation

The promoter has declared 21 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Bombay High Court56/20172017Court Is In Process Of Appointing Arbitrator
Kalyan Court235/Spl cs 20162016Proceedings Going On
Kalyan Court163/RCS 20162016Proceedings Going On
Kalyan Court112/20172017Rtg Cannot Be Dispossesed Of Its Project
Kalyan Court174/20082008Proceedings Going On
Kalyan Court182/20172017Proceedings Going On For Kdmc Open Land Tax Dispute Property Ceased By Kdmc And Bank Account Freeze
Kalyan Police StationComplaint2011Filed By Rtg At Bazar Peth Against Copromoters Saibaba Developers And Partners For Cheque Bounce
Bandra Court2890/ss 20152015Filed Against Saibaba And Suresh Wadhwa And Shankar Rohra And Prakash Rohra And Others
Kalyan Police StationComplaint2013Rtg Filed Complaing Against Saibaba Developers And Partners For Noncompliance With Development Agmt
Kalyan Police StationComplaint2015Filed By Rtg Againt Saibaba Developers For Cheque Bounce And Nonclearance Of Rg
Thane Police CommissionarComplaint2017Filed By Rtg Against Saibaba Developers And Partners And Havesh Deshmukh And Family
Consumer Court ThaneCC 3102013Case For Delay In Possession
Consumer Court ThaneCC 3112013Case For Delay In Possession
Consumer Court ThaneCC 3122013Case For Delay In Possession
Consumer Court ThaneCC 3132013Case For Delay In Possession
Bombay High Court413 of 20172017Filed Against Police Department To Take Action Against Saibaba And Its Partners
Kalyan Court649/20172017Anticipatory Bail Granted By Court
Crime Branch ThaneComplaint2017Complaint Gainst Havesh Narendra Deshmukh For Not Allowing Construction Of Project
Crime Branch ThaneIntimation2017Intimation Of Current Satus Of Courts Direction For Appointment Of Arbitrators
Bombay High Court7282015Company In Liquidation
Bombay High Court8452015Company In Liquidation

Location, Land & Connectivity

Located at kalyan, 106 part, Andheri, Mumbai Suburban, 421301. Per the filed land record, the plot is bounded to the north by 12 M Wide Road, to the south by Chawl, to the east by 18 M Wide Road and to the west by Open Land. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~28 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park28 km
Andheri MIDC / SEEPZ30 km
Chhatrapati Shivaji Int'l Airport33 km
Bandra Kurla Complex (BKC)34 km
Lower Parel / Worli business district42 km
Nariman Point / Fort48 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kalyan

Bhushan Anand CO OP HSG SOC
possession by Sep 2026 · Dinesh Laxman Sonavane
Ishanvi Ashapura Tower
possession by Sep 2026 · Ishanvi Ashapura Developers
Keshar Aagan Cooperative Housing Society
possession by Sep 2026 · Gagan Homes
Mohan Deep
possession by Sep 2026 · Sunil Purushottam Deshmukh
Parshuram Tower
possession by Sep 2026 · Moreshwar Constructions
Ritz Phase II Commercial Tower D
possession by Sep 2026 · Vikas Harakchand Jain

Major developers building in Kalyan

Other RERA-registered projects in Thane

Ruby Height
possession by Aug 2029 · Ramiz Sikandar Ahmad Patel
Ruby Roof Makers
declared completion May 2022 · Ruby Roof Makers
Rucha Vatika D Wing Orchid E Wing Iris
possession by Dec 2028 · Milan Housing Complex PVT LTD
Rudra Apartment
declared completion Mar 2024 · Shreenath Constructions
Rudra Apartment
possession by Jul 2027 · Indoria & Sons Realtors LLP
Rudra Avenue
possession by Dec 2028 · Krivi Construction

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026