Mumbai/Project record

MahaRERA · the public record

RUDRA HEIGHTS

RAM MANDIR CORNER · A.S.D. ENTERPRISES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700027142

Delivery and registration

When is the project declared for completion?

RUDRA HEIGHTS is registered with MahaRERA as P51700027142 and the promoter has declared completion for 30 Dec 2024.

30 Dec 2024

declared completion

21months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700027142
Registered on19 Nov 2020
Promoter-declared completion30 Dec 2024
Current statusCertificate Signed
Against todayabout 21 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for RUDRA HEIGHTS record 17 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 17 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for RUDRA HEIGHTS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+14.

BuildingWingsFloorsDeclared completion
WING A1G+630 Jun 2023
WING B1G+1430 Jun 2023

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Dec 2024As we are aware the entire nation was passing through a Pandemic being COVID-19. Covid-19 infections were took pickup in the month of Feb-21, we could not start our development wor

Location, Land & Connectivity

Located at RAM MANDIR CORNER, DEENDAYAL ROAD, Kalyan, Thane, 421202. Per the filed land record, the plot is bounded to the north by SONGYA MHATRE BUILDING, to the south by 12 MW D P ROAD, to the east by SHIVAM TOWER BUILDING AND SHIV MANDIR and to the west by BUDHAJI TOWER BUILDING. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~22 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park22 km
Andheri MIDC / SEEPZ25 km
Chhatrapati Shivaji Int'l Airport27 km
Bandra Kurla Complex (BKC)28 km
Lower Parel / Worli business district36 km
Nariman Point / Fort43 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Dombivli West

Amar Elegance
possession by Sep 2026 · Amar Realty
Purva Prime
possession by Sep 2026 · Trimurti Constructions
Anant AND Radhika Heights
possession by Dec 2026 · Ashapura Construction CO
Chintamani Heights & Chintamani Kuber
possession by Dec 2026 · Chintamani Developers
Indira Galaxy
possession by Dec 2026 · Shree Developers
Jai Shree Ganesh Co-Operative Housing Society Limited
possession by Dec 2026 · Shree Vyankatesh Enterprises

Major developers building in Dombivli West

Other RERA-registered projects in Thane

Rudra Infra
declared completion Apr 2024 · MS Rudra Infra THR Porp Amol B Kaduskar
Rudra Residency
possession by Aug 2028 · S R Choudhari Construction
Rudra VAN
declared completion Dec 2025 · Shivkrupa Realty
Rudraa Residency
declared completion Jun 2020 · Ritu Developers
Rudraksh Tower
declared completion Mar 2026 · Shivshakti Builders AND Developers
Rudraraj Complex
possession by Dec 2028 · Ravi Chahu Patil

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026