Saavi Empire

Kamothe · S B Construction

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

6units filed as unsoldInventory · 18 September 2026
30 Apr 2028declared completionMahaRERA registration · read 10 Sep 2026
12registered unitsMahaRERA registration · read 10 Sep 2026

The record · free to read

Registration read 10 Sep 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Apr 2028

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 10 Sep 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · PR1270002601049

Delivery and registration

When is the project declared for completion?

Saavi Empire is registered with MahaRERA as PR1270002601049 and the promoter has declared completion for 30 Apr 2028.

30 Apr 2028

declared completion

19months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 10 Sep 2026

MahaRERA registrationPR1270002601049
Registered on06 Jul 2026
Promoter-declared completion30 Apr 2028
Current statusCertificate Signed
Against today19 months to the declared date

Sales

How much has actually been sold?

In Saavi Empire, 0 of 6 homes filed with MahaRERA are recorded as sold or booked, about 0%, and 6 remain available.

0%sold

0 of 6 homes

Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. The project registers 12 homes in total, while this sold/unsold inventory filing covers 6 of them.

Source · MahaRERA sold/unsold inventory filing · read 10 Sep 2026

The units recorded as unsold on the filing. The reckoner value is the government's ready-reckoner assessment the promoter filed against that unit, the figure stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home.

FloorUnitCarpetGovt reckoner value
Floor 1101178 sqft (16.5 sqm)₹17.94 Lakh
Floor 1102266 sqft (24.72 sqm)₹26.87 Lakh
Floor 1103323 sqft (29.98 sqm)₹32.60 Lakh
Floor 2201178 sqft (16.5 sqm)₹17.94 Lakh
Floor 2202266 sqft (24.72 sqm)₹26.87 Lakh
Floor 2203323 sqft (29.98 sqm)₹32.60 Lakh

The inventory filing also declares: 6 not for sale.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Saavi Empire in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 September 2026

What the filings record, home by home

Read from MahaRERA on 18 September 2026

No home in Saavi Empire carries a registered agreement value on its MahaRERA filing, so there is no record here of what anyone has paid. What the promoter has filed is the government ready reckoner value for 6 homes — the Annual Statement of Rates valuation, with each home’s carpet area and floor already applied. Across them that is Rs 10,100 a sq ft typical, over Rs 10,099 to Rs 10,101.

A reckoner value is the basis stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home to you.

The Reckoner Record lists all 6 of them — each home, its RERA carpet area, the valuation filed against it and the rate that works out to. It is the filing copied, not a reading of it.

See all 6 filed valuations — ₹999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4 and 12 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Saavi Empire1G+412-

Unit mix on the filing: 12 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Civil Court Senior Division Panvel390/20232023Ongoing

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Apr 2028NA

Location, Land & Connectivity

Located at Kamothe, Plot No 3C, Sector-17, Panvel, Raigarh, 410209. Per the filed land record, the plot is bounded to the north by Gaothan Road., to the south by 3.00 Mtrs. Wide Road., to the east by Prop. 6 Mtrs Wide Road. and to the west by Plot No. 3D.. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~22 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park22 km
Bandra Kurla Complex (BKC)24 km
Chhatrapati Shivaji Int'l Airport25 km
Andheri MIDC / SEEPZ26 km
Lower Parel / Worli business district27 km
Nariman Point / Fort29 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Not Available is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Not Available

Not Available
FlaggedMumbai Suburban

Other RERA-registered projects in Kamothe

Plot No -2,sector-39,mansarovar Railway Station
possession by Dec 2026 · City AND Industrial Development Corporat
Raghunath
possession by Dec 2026 · Aayushi Corporation
Aayushi Empire
possession by Sep 2027 · Aayushi Construction
SAI Krupa
possession by Sep 2027 · K T Realty
Bhaveshwar Aatma Sadan
possession by Dec 2027 · Bhaveshwar Construction
ND Pearl
possession by Dec 2027 · Shree Gajanand Infra

Other RERA-registered projects in Raigarh

Saavi Residency
possession by May 2028 · Not Available
Sachin Bipin Residency
declared completion Apr 2026 · Laxmi Narayan Realty
Sadaf Residency
declared completion May 2026 · Magma Infra
Sadanalini Residency
declared completion Aug 2026 · Azaruddin Patel
Sadashiv Laxmi
possession by Dec 2027 · Raju Ratnakumar Sali
Sadbhavna Apartment
declared completion May 2023 · Sanjay Rambadan Tiwari

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026