MahaRERA Property Intelligence · Palghar

Sadguru Aarambh

P99000021488 · Saphale West · promoter Visharia Sadguru Bhoomi

Certificate SignedDue 30 Mar 2023

Delivery & Registration

MahaRERA registrationP99000021488
Registered on05 Jul 2019
Promoter-declared completion30 Mar 2023
Current statusCertificate Signed
Against todayabout 40 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Visharia Sadguru Bhoomi is the promoter of record on 3 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
Sadguru Aarambh-A wing1G+431 Mar 2022
Sadguru Aarambh-B wing1G+431 Mar 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Mar 202330 Sep 2023We have obtained OC of the Building and uploaded the same. We have Started process of Society Formation, However we have not been able to form the Society due to some reason or the

Location, Land & Connectivity

Located at Saphale West, Panditpada, Mumbai City, Mumbai City, 401102. Per the filed land record, the plot is bounded to the north by Building No22, to the south by 9mt Wide Layout Road, to the east by Building No15 and to the west by Building No 17. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~140 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park140 km
Andheri MIDC / SEEPZ141 km
Chhatrapati Shivaji Int'l Airport145 km
Bandra Kurla Complex (BKC)147 km
Lower Parel / Worli business district156 km
Nariman Point / Fort163 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Visharia Sadguru Bhoomi LLP is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Visharia Sadguru Bhoomi LLP

Visharia Sadguru Bhoomi LLP
FlaggedPalghar

Other RERA-registered projects in Makane

Galaxy Complex
possession by Jul 2026 · Ksquare Realty Private Limited
Balaji Heights
possession by Dec 2026 · Tirupati Enterprises
Excellence Residency 2
possession by Dec 2026 · SAI Excellence Realtors
Excellence Residency 3
possession by Dec 2026 · SAI Excellence Developers
Nayan-Vastu Heritage
Not filing quarterly progress reports · possession by Dec 2026 · Unity Infra
Nayan-Vastu Heritage
possession by Dec 2026 · Unity Infra

Major developers building in Makane

Other RERA-registered projects in Palghar

Sadguru Empire
declared completion Jun 2026 · Guru Prasad Construction Company
Sadguru Heights
declared completion Dec 2023 · Sadguru Devlopers
Sadguru Heights
declared completion Jun 2026 · Shree Sadguru Builders & Developers
Sadguru Tower Bldg NO 2
possession by Dec 2027 · Visharia Sadguru Bhoomi LLP
Safalya
declared completion Aug 2022 · Chandrashekhar Shantaram Dhuri
Sagar Complex
declared completion Dec 2023 · Sakla Enterprises

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026