MahaRERA Property Intelligence · Thane

SAGAR ACCORD

P51700017916 · mira road east · promoter Realty

Certificate SignedDue 30 Dec 2021

Delivery & Registration

MahaRERA registrationP51700017916
Registered on25 Sep 2018
Promoter-declared completion30 Dec 2021
Current statusCertificate Signed
Against todayabout 55 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
SAGAR ACCORD1G+431 Dec 2020

Complaints & Orders

1 complaint is on the MahaRERA record for this project, with orders passed in 1. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000019590706/02/2021MANOJ P FADIA vs M/S. S A REALTYorder passed

Location, Land & Connectivity

Located at mira road east, beverly park , Thane, Thane, 401107. Per the filed land record, the plot is bounded to the north by kinza apartment, to the south by stanley paradise, to the east by silver oak complex and to the west by shanzam apartment. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~18 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ18 km
Powai / Hiranandani business park20 km
Chhatrapati Shivaji Int'l Airport23 km
Bandra Kurla Complex (BKC)25 km
Lower Parel / Worli business district33 km
Nariman Point / Fort41 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Mira Road East

Ganesh Darshan
possession by Jul 2026 · J.v. Realty
Savaliya Residency
possession by Jul 2026 · Shree Savaliya Housing LLP
127 RAJ Homes A Wing
possession by Aug 2026 · RAJ Homes
Beaumonde
possession by Sep 2026 · Kanungo Property
Rassaz Greens Tower C D AND E
possession by Dec 2026 · Rassaz Infrastructure Private Limited
Coral
Deregistered by MahaRERA · possession by Dec 2026 · Nilesh Shantilal Tank

Major developers building in Mira Road East

Other RERA-registered projects in Thane

Sagar Apt
possession by Jul 2027 · Silver & Rashi Constructions
Sagar Bliss
possession by Jun 2029 · Sagar Enterprises
Sagar Enclave
possession by Dec 2026 · Kanchan Builders & Developers
Sagar Greens
possession by Dec 2026 · Sagar Greens
Sagar Heights
declared completion Jun 2026 · Aadinath Developers
Sagar Homes
declared completion Dec 2025 · M/S Sagar Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026