Sahakar Residency

P51700009131 · Juchandra Naigaon east · promoter Sahakar Infracon Projects

Certificate SignedDue 31 Dec 2018

Delivery & Registration

MahaRERA registrationP51700009131
Registered on19 Aug 2017
Promoter-declared completion31 Dec 2018
Current statusCertificate Signed
Against todayabout 91 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Sahakar Infracon Projects is the promoter of record on 189 projects, of which 18 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+10.

BuildingWingsFloorsDeclared completion
Sahakar Residency1G+1031 Dec 2018

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Dec 201831 Dec 2018Due to delay in electricity connection by MSEB, Further we will apply for OC as soon as we are done with electricity connection.

Location, Land & Connectivity

Located at Juchandra Naigaon east, Tivri Road, Mumbai City, Mumbai City, 401207. Per the filed land record, the plot is bounded to the north by 30 mtrs wide DP road, to the south by Survey no 348 to south, to the east by 1 2 School Building and to the west by Building No 4. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~26 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ26 km
Powai / Hiranandani business park28 km
Chhatrapati Shivaji Int'l Airport30 km
Bandra Kurla Complex (BKC)33 km
Lower Parel / Worli business district41 km
Nariman Point / Fort49 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Sahakar Infracon Projects Private Limited is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Sahakar Infracon Projects Private Limited

Sahakar Infracon Projects Private Limited
FlaggedThane

Other RERA-registered projects in Papdy

Govind Enclave
possession by Aug 2026 · M/s Divekar And Patil Construction
AVF Greens
possession by Dec 2026 · A.v.f. Realty
Nilkant Sadan
possession by Dec 2026 · Divija Developers
SKY Vista
possession by Dec 2026 · M/s. Divine Construction
Redevelopment Of Chinmay Co-Operative Housing Society Ltd
possession by Jan 2027 · Neom Construction
Premier Elegance
possession by Mar 2027 · Premear Landmark Developers LLP

Other RERA-registered projects in Palghar

Sahara Regency
declared completion May 2025 · S. G. Builders AND Developers
Sahara Residency
possession by Dec 2028 · Suresh Manvel Gonsalves
Sahayog Heights
declared completion Dec 2025 · Dsquare Buildcon LLP
Sahyadri Classic
possession by Dec 2028 · Sahyadri Developers
SAI Aangan
declared completion Dec 2021 · S A Infra
SAI Aarti
possession by Dec 2026 · SAI Thiya Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026