Mumbai/Project record

MahaRERA · the public record

Sai Darshan

Sai Road, Masoli · DINESH SADANAND BARI

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

15 Dec 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

15 Dec 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000025168

Delivery and registration

When is the project declared for completion?

Sai Darshan is registered with MahaRERA as P99000025168 and the promoter has declared completion for 15 Dec 2022.

15 Dec 2022

declared completion

45months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000025168
Registered on20 Mar 2020
Promoter-declared completion15 Dec 2022
Current statusCertificate Signed
Against todayabout 45 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Sai Darshan record 12 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 12 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Dinesh Sadanand Bari is the promoter of record on 24 projects registered with MahaRERA, 4 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

24projects

registered with MahaRERA

4flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Sai Darshan in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
Type A1G+430 Oct 2021
Type B1G+415 Oct 2021
Type C21G+430 Nov 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. 1 is still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Civil Judge Junior Division DahanuRegular Civil Suit No 108 20152015Pending

Location, Land & Connectivity

Located at Sai Road, Masoli, Main Road, Dahanu, Palghar, 401602. Per the filed land record, the plot is bounded to the north by Kapadiya Building, to the south by 6 meter wide Road, to the east by St Marrys Highschool Ground and to the west by 18 meter DP Road. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Dinesh Sadanand Bari is the promoter on 2 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other RERA-registered projects in Ashagad

Ratnamani Residency A
possession by Dec 2026 · Bhavi Reality LLP
SAI Garden Residency
Not filing quarterly progress reports · possession by Mar 2027 · Shahji Enterprises
Samruddhi Apartment
possession by Dec 2027 · Not Available
Shambhavi Apartments
possession by Dec 2028 · Jayesh Balvant Jani
Shambhavi ROW Houses Phase 2
possession by Dec 2028 · Jayesh Balvant Jani
Landmark
possession by Apr 2029 · Anmol Developers

Other RERA-registered projects in Palghar

SAI Darshan
possession by Dec 2026 · SAI Shraddha Enterprises
SAI Darshan Apartment
declared completion Dec 2022 · Sai Jayshree Developers
SAI Darshan Apartment
declared completion Dec 2024 · SAI Homes
Sai Dham
declared completion Jun 2021 · Shreeji Developers
SAI Dham
possession by Apr 2027 · Badshah Baba Realtors & Developers L
SAI Garden Residency
possession by Mar 2027 · Shahji Enterprises

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026